Quarterly Activities Report
Released
Released
Announcement PDF
29 January 2021
Quarterly Activities Report
The following is a summary of the activities conducted by VRX Silica Ltd (VRX or Company)
(ASX: VRX) during the quarter ending 31 December 2020.
Arrowsmith Silica Sand Projects
Native Title Clearance
VRX holds the Arrowsmith North and Arrowsmith Central Silica Sand Projects (Arrowsmith
Projects), which are located 270km north of Perth, in its wholly owned subsidiary Ventnor
Mining Pty Ltd.
In October 2020, conclusive registration of the Yamatji Nation Indigenous Land Use Agreement
(ILUA) occurred, which cleared the pathway for grant of the Company’s Mining Lease and
Miscellaneous Licence applications for its Arrowsmith Projects.
The ILUA is an alternative settlement by the Western Australian Government of native title
claims covering a significant portion of land in the Mid West, including the Southern Yamatji
People’s claim covering the Arrowsmith Projects.
This Government-led ILUA settled all native title claims over the Arrowsmith Projects area and
superseded the negotiations that had been progressing in good faith between VRX and the
Southern Yamatji People native title claimants over the Arrowsmith Projects. The strong and
supportive relationships established with the Southern Yamatji People will continue to benefit
all parties as the Arrowsmith Projects are developed, and the Company intends to continue to
consult with the Southern Yamatji People.
Aboriginal Heritage Survey
In November 2020, VRX announced the results of an Aboriginal heritage survey at its
Arrowsmith Projects.
The comprehensive archaeological and ethnographic survey was conducted during October
with Amangu representatives of the Yamatji Nation and Yamatji Marlpa Aboriginal Corporation
(YMAC) personnel over proposed initial mining and critical infrastructure areas.
The survey found no isolated artifacts and no onerous heritage recommendations were made.
Preliminary advice received by the Company from YMAC confirmed that the Arrowsmith North
Access Road, Services Corridor and Production Area have been cleared for the stated works
to proceed for 10 years of production. The Arrowsmith Central Production Area and Arrowsmith
Central Infrastructure Areas are cleared for 5 years of production. See Figure 1.
Figure 1: Critical infrastructure and mining areas surveyed at Arrowsmith North and Arrowsmith Central.
Grant of Mining Leases
On 17 November 2020, VRX announced the grant of Mining Leases for its Arrowsmith Projects
(see Figure 2). This, together with the Aboriginal heritage clearance for the proposed works
on both projects, is an important step forward for their development. The combined Mining
Lease areas cover over 3,600ha, sufficient for over 100 years of production.
The grant of these Mining Leases was another significant milestone for the Company and came
shortly after the grant of the Mining Lease for VRX’s Muchea Silica Sand Project (see
commentary below). It enables the Company to step up negotiations to finalise sales contracts
for the high-quality silica sand products and secure the necessary funding for their
development.
Figure 2: Arrowsmith Silica Sand Project Location
Muchea Silica Sand Project
Grant of Mining Lease
On 29 October 2020, VRX announced the grant of a Mining Lease for its Muchea Silica Sand
Project (Muchea Project), located 50km north of Perth, Western Australia. The Mining Lease
(M70/1390) covers approximately 1,008ha including the development area, sufficient for at
least 25 years of production (see Figure 3).
Figure 3: Muchea Silica Sand Project Location
The grant of the Mining Lease was a significant milestone for VRX and a major step forward in
the journey to becoming a global, long-life supplier of high-quality silica sand.
Demand from potential customers for long-term supply of silica sand from the Muchea Project
is strong. As for the Company’s Arrowsmith Projects, the grant of the Mining Lease enables
the Company to step up negotiations to finalise sales contracts for the high-quality silica sand
products and secure the necessary funding for the project’s development.
The Muchea Silica Sand Project is a world-class, high-grade and low environmental impact
silica sand project with outstanding economics and located in a Tier 1 jurisdiction. Its
development will support a substantial export industry in Western Australia and provide
significant financial and employment benefits in the north-eastern corridor of Perth.
Project Economics
The Company’s three projects have outstanding economic prospects and will support a
substantial export industry in Western Australia providing significant financial and employment
benefits to the State.
With all three Mining Leases granted and development of the projects on-track, VRX is truly a
global player in high-quality silica sand supplies.
ARROWSMITH NORTH
Project Location
Arrowsmith North is located approximately 270km north of Perth between the regional
Western Australian towns of Eneabba and Dongara (see Figure 1 and Figure 2). The project
sits proximate to Brand Highway and is connected to the Geraldton Port via the EneabbaGeraldton Railway.
Mineral Resource and Ore Reserve
The Mineral Resource Estimate (MRE) for Arrowsmith North comprises an Indicated Mineral
Resource of 248 Mt @ 97.7% SiO2 in addition to an Inferred Mineral Resource of 523 Mt
@ 98.2% SiO2 for a Total MRE of 771 Mt @ 98.0% SiO21 reported in accordance with the
JORC Code2 (Table 1).
1 ASX announcement of 9 July 2019, “Arrowsmith North Mineral Resource Estimate Upgrade”
2 Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves, 2012 Edition
(JORC Code).
Classification
Domain
Million Tonnes
SiO2%
Al2O3%
Fe2O3%
TiO2%
LOI%
Indicated
White Sand
33
98.7
0.50
0.20
0.20
0.20
Yellow Sand
215
97.5
1.10
0.40
0.20
0.50
All Sand
248
97.7
1.00
0.40
0.20
0.50
White Sand
280
98.7
0.50
0.10
0.20
0.20
Yellow Sand
243
97.7
1.00
0.40
0.20
0.50
All Sand
523
98.2
0.80
0.30
0.20
0.40
White Sand
313
98.7
0.54
0.15
0.18
0.24
Yellow Sand
458
97.6
1.08
0.40
0.17
0.52
All Sand
771
98.0
0.86
0.30
0.17
0.41
Inferred
Indicated +
Inferred
*Note: Interpreted silica sand mineralisation is domained above a basal surface wireframe defined based on drill logging data. The
upper (Topsoil) layer within 0.5 m of surface is depleted from the modelled silica sand unit, being reserved for rehabilitation
purposes. All classified silica sand blocks in the model are reported. Differences may occur due to rounding.
Table 1: Arrowsmith North Mineral Resource Estimate
The Company completed the necessary work to convert the Indicated Mineral Resource to
Probable Ore Reserve3. Table 2 details the Probable Ore Reserve reported in accordance with
the JORC Code that will be produced from mining of the Indicated Mineral Resource and
processing in a purpose-built, wet-sand processing plant.
Recovery
Million
Tonnes
Within
M70/1389
Million
Tonnes
Arrowsmith-N20
24%
60
54
99.7
0.2
0.05
0.035
0.1
Arrowsmith-N40/
NF500
60%
149
136
99.7
0.2
0.05
0.035
0.1
Local Market
6%
15
14
223
204
Global
Chemical Composition
Classification
Probable
Product
Total Reserve
SiO2
%
Al2O3
%
Fe2O3
%
TiO2
%
LOI
%
Table 2: Arrowsmith North Probable Ore Reserve
Production Target
The Company has set out in the Arrowsmith North bankable feasibility study (BFS) a
production target of 47.7Mt from the first 25 years of mine life at Arrowsmith North, reported
in accordance with the JORC Code, sourced from the Probable Ore Reserve of 204Mt @
99.7% SiO2 within the Mining Lease (M70/1389) area.
Full details are set out in the Arrowsmith North BFS4.
3 ASX Announcement of 28 August 2019, “Arrowsmith North BFS and Maiden Ore Reserve”
4 ASX Announcement of 28 August 2019, “Arrowsmith North BFS and Maiden Ore Reserve”
Silica Sand Products
Based on metallurgical test work completed to-date, the silica sand at Arrowsmith North is
readily amenable to upgrading by conventional washing and screening methods to produce a
high-purity silica sand product with high mass recoveries. The high-purity silica sand product
specifications are expected to be suitable for industries such as glass making and foundry
sand. The plant will produce four saleable products for different markets. Table 3 shows the
particle-size distribution of the products.
Sieve Opening (Mesh/μm Retained)
Particle Size
Product
10 /
2mm
20 /
850
30 /
600
40 /
425
50 /
300
70 /
212
140 /
106
0.10%
100 /
150
-
AFS
No
-
200 /
75
-
Arrowsmith-N20
0.10%
3%
87%
8%
1%
Arrowsmith-N40
-
0%
21%
36%
24%
13%
5%
1%
0%
36
Arrowsmith-NF500
-
-
0.50%
40%
42%
17%
1%
0%
-
38
Local Market
-
-
-
-
-
-
64%
22%
14%
-
21
Table 3: Arrowsmith North saleable products, particle size distribution
Permitting
During the quarter VRX submitted a formal referral to the Federal Department of Agriculture,
Water and Environment (DAWE). Subsequent to the end of the quarter the Company will
follow with a formal referral to the State Department of Water and Environmental Regulation
(DWER) to secure environmental approvals for the development of Arrowsmith North. Prereferral meetings with representatives from DAWE and the DWER have provided valuable
feedback as to requirements for these referrals.
The Company will also expedite approval for its mine plan and the issue of a mining permit
from the Department of Mines, Industry Regulation and Safety (DMIRS).
ARROWSMITH CENTRAL
Project Location
Arrowsmith Central is located approximately 270km north of Perth between the regional
Western Australian towns of Eneabba and Dongara (see Figure 1 and Figure 2). The project
sits proximate to Brand Highway and is connected to the Geraldton Port via the EneabbaGeraldton Railway.
Mineral Resource and Ore Reserve
The Mineral Resource Estimate (MRE) for Arrowsmith Central comprises an Indicated Mineral
Resource of 28.2 Mt @ 96.6% SiO2 in addition to an Inferred Mineral Resource of 48.3 Mt
@ 96.9% SiO2, for a Total MRE of 76.5 Mt @ 96.8% SiO2 5 reported in accordance with the
JORC Code (Table 4).
Classification
Million Tonnes
SiO2%
Al2O3%
Fe2O3%
TiO2%
LOI%
Indicated
28.2
96.6
1.7
0.4
0.2
0.7
Inferred
48.3
96.9
1.5
0.4
0.2
0.7
Indicated + Inferred
76.5
96.8
1.5
0.4
0.2
0.7
* Note: Interpreted silica sand mineralisation is domained above a basal surface wireframe defined based on drill sampling
depths. A depletion zone, consisting of the upper 0.5 m, is reserved for rehabilitation purposes and is not estimated or reported.
Differences may occur due to rounding.
Table 4: Arrowsmith Central Silica Sand Mineral Resource Estimate
The Company completed the necessary work to convert the Indicated Mineral Resource to
Probable Ore Reserve. Table 5 below details the Probable Ore Reserve that will be produced
from the mining of the Indicated Mineral Resource and processing in a purpose built, wet sand
processing plant.
Product
Recovery
Million
Tonnes
Within
M70/1392
Million
Tonnes
Arrowsmith-CF400
17%
4.2
4.1
Arrowsmith-C20
34%
8.4
8.2
Arrowsmith-C50
17%
4.2
4.1
TiO2 Concentrate
9%
2.2
2.2
18.9
18.7
Global
Chemical Composition
Classification
Probable
Total Reserve
SiO2
%
Al2O3
%
Fe2O3
%
TiO2
%
LOI
%
99.6
0.25
0.04
0.03
0.1
<1%
+2%
Table 5: Arrowsmith Central Probable Ore Reserve
5ASX announcement of 15 August 2019, “Arrowsmith Central Mineral Resource Estimate Upgrade”.
Production Target
The Company has set out in the Arrowsmith Central BFS a production target of 18.9 Mt @
99.6% SiO2 as reported in accordance with the JORC Code with 18.7 Mt @ 99.6% SiO 2
contained within the area of the Company’s Mining Lease (M70/1392).
Full details are set out in the Arrowsmith Central BFS6.
Silica Sand Products
Based on metallurgical test work completed to-date, the silica sand at Arrowsmith Central is
readily amenable to upgrading by conventional washing and screening methods to produce a
high-purity silica sand product with high mass recoveries. The high-purity silica sand product
specifications are expected to be suitable for industries such as glass making and foundry
sand.
The plant will produce three saleable silica sand products for different markets. Table 6 shows
the particle-size distribution of the products.
Sieve Opening (Mesh / μm Retained)
Particle Size
Product
10 /
2mm
20 /
850
30 /
600
40 /
425
50 /
300
70 /
212
140 /
106
16.1%
100 /
150
0.5%
Arrowsmith-CF400
-
0%
0.5%
44%
38.9%
Arrowsmith-C20
6.2%
22.2%
30.4%
37.9%
Arrowsmith-C50
-
-
0.3%
31.9%
AFS
No
-
200 /
75
-
2.9%
0.3%
0.1%
-
-
22
27.5%
17.3%
13.7%
8.2%
1.1%
49
37
Table 6: Arrowsmith Central Silica Sand Probable Ore Reserve
In addition to these products, the plant will produce a by-product that contains a concentration
of titanium minerals such as rutile and ilmenite which can be sold at a nominal value to a
company with specialist equipment for separating mineral concentrate (see Table 5 for
summary of TiO2 concentrate).
Permitting
VRX will submit formal referrals to the Federal DAWE and the State DWER to secure
environmental approvals for the development of Arrowsmith Central. Pre-referral meetings
with representatives from DAWE and the DWER have provided valuable feedback as to
requirements for these referrals.
The Company will also seek to expedite approval for its mine plan and the issue of a mining
permit from DMIRS.
6 ASX Announcement of 17 September 2019, “Arrowsmith Central BFS and Maiden Ore Reserve”
MUCHEA
Project Location
The Muchea Project is located 50km north of Perth between the regional West Australian
towns of Muchea and Gingin (see Figure 3) and sits adjacent to Brand Highway and the
Moora–Kwinana Railway, with a rail connection direct to the multi-user Kwinana Bulk Terminal.
Mineral Resource and Ore Reserve
The Mineral Resource Estimate (MRE) for the Muchea Project comprises 208Mt @ 99.6%
SiO27 reported in accordance with the JORC Code8 (Table 7).
The MRE is based on the results obtained from 44 hand auger drill holes for 260.7m and 103
air core (AC) drill holes for 1,401m used to define the modelled silica sand layer.
Classification
Million Tonnes
SiO2%
Al2O3%
Fe2O3%
LOI%
TiO2%
Indicated
29
99.6
0.09
0.03
0.22
0.07
Inferred
179
99.6
0.05
0.02
0.23
0.1
Indicated + Inferred
208
99.6
0.06
0.02
0.23
0.1
*Note: Interpreted silica sand mineralisation is domained above a basal surface wireframe. The upper (overburden)
layer within 0.5 m of surface is depleted from the modelled silica sand unit, being reserved for rehabilitation purposes.
All classified silica sand blocks in the model are reported. Differences may occur due to rounding.
Table 7: Muchea Mineral Resource Estimate
The Company has completed the necessary work to convert the Indicated Mineral Resource to
Probable Ore Reserve9. Table 8 details the Probable Ore Reserve reported in accordance with
the JORC Code that will be produced from mining of the Indicated Mineral Resource and
processing in a purpose-built, wet-sand processing plant.
Product
Recovery
Million
Tonnes
Within
M70/1390
Million
Tonnes
Muchea-F80
48%
10.2
8.0
+99.9
0.02
0.008
0.030
0.1
Muchea-F80C
20%
4.25
3.3
+99.9
0.02
0.008
0.030
0.1
Muchea-F150
20%
4.25
3.3
99.8
0.07
0.015
0.035
0.1
18.7
14.6
Global
Ore Reserve
Classification
Probable
Total Reserve
SiO2
%
Al2O3
%
Fe2O3
%
TiO2
%
LOI
%
Table 8: Muchea Silica Sand Probable Ore Reserve
7 ASX announcement of 17 June 2019, “Muchea Mineral Resource Estimate Upgrade”.
8 Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves, 2012 Edition
(JORC Code).
9 ASX Announcement of 18 October 2019, “Muchea BFS and Maiden Ore Reserve”
Initial Production Target
The Company has set out in the BFS an initial production target of 48.3Mt from the Muchea
Project reported in accordance with the JORC Code, sourced from the Probable Ore Reserve
of 14.6Mt @ 99.9% SiO2 and a portion of the Inferred Mineral Resource of 61.4Mt @ 99.6%
SiO2 within the Mining Lease area.
The maiden Probable Ore Reserve is estimated from the Indicated Mineral Resource only and
constitutes approximately 30% of the estimated total production target (in terms of processed
tonnes of silica sand) over a 25-year mine life. The Company intends to mine solely from the
Probable Ore Reserve during the first nine to 10 years of mining operations.
The ore that forms the Inferred Mineral Resource is contiguous with the Indicated Mineral
Resource and has been categorised as lower confidence because of wider-spaced drilling.
There is negligible difference between the modelled sand in each category and it is believed
an additional 1,500m of drilling would be required to upgrade the inferred resource category.
Notwithstanding this, there is a low level of geological confidence associated with inferred
mineral resources and there is no certainty that further exploration work will result in the
determination of indicated mineral resources or that the production target itself will be realised.
Full details are set out in the BFS.10
Silica Sand Products
Based on metallurgical test work completed to-date, the silica sand at Muchea is readily
amenable to upgrading by conventional washing and screening methods to produce a highpurity silica sand product with high mass recoveries. The high-purity silica sand product
specifications are expected to be suitable for industries such as glass making and foundry
sand.
The plant will produce three saleable products for different markets with a Probable Ore
Reserve of 14.6Mt @ 99.9% SiO2 reported in accordance with the JORC Code contained
within the area of the Mining Lease.
Table 9 shows the particle-size distribution of the products.
Sieve Opening (μm Retained)
Particle Size
Product
850
Muchea-F80
Muchea-F80C
Muchea-F150
9.0%
600
425
300
212
0.5%
49%
50%
0.5%
90.0%
1.0%
0.5%
88%
Table 9: Muchea saleable products, particle size distribution
10 ASX Announcement of 18 October 2019, “Muchea BFS and Maiden Ore Reserve”
150
106
11%
0.5%
75
The Muchea Project has outstanding economic prospects. Key outcomes from the BFS11 and
summary financial model outputs are set out below.
Muchea
(including Inferred)
Muchea
(Reserve only)
Post Tax, ungeared NPV10
$337,900,000
$180,500,000
Post Tax, ungeared NPV20
$146,400,000
$104,600,000
Post Tax, ungeared IRR
96%
96%
Payback period (yrs) (post tax) (ramp up rate)
2.3
2.3
Exchange Rate US$/A$
$0.70
$0.70
Life of Mine (yrs) (Scope of BFS Study)
25
15
Total Sales (initial 25 years) no escalation
$3,345,000,000
$1,011,000,000
EBIT
$1,540,000,000
$447,000,000
Cashflow after finance and tax
$1,123,000,000
$321,000,000
404,318,617
404,318,617
$0.11
$0.09
$32,820,000
$32,820,000
Capex contingency (inc)
20%
20%
Life of Mine C1 costs, FOB Kwinana (inc royalties)
$32.74
$33.84
54
16
Shares on Issue
EPS after tax (per year)
Capex (2 mtpa)
Tonnes Processed (initial 25 years) (Mt)
Production Target (Mt) (BFS Study)
(25 years) 48.3
(9-10 years) 14.6
Probable Ore Reserves @ 99.9% SiO2 (Mt)
18.7
18.7
Ore Reserve life (yrs)
9-10
9-10
JORC Resources (million tonnes)
208
208
Notes:
1. The first column shows outputs when aggregated with the Inferred Mineral Resource and the second column
shows outputs from the Probable Ore Reserve only.
2. There is a low level of geological confidence associated with inferred mineral resources and there is no certainty
that further exploration work will result in the determination of indicated mineral resources or that the production
target itself will be realised.
3. The Probable Ore Reserve and the Inferred Mineral Resource underpinning the above production targets have
been prepared by a Competent Person in accordance with the requirements of the JORC Code.
4. Full summaries of economic assumptions are set out in the BFS. All such material assumptions continue to apply
and have not materially changed from the date of release of the BFS.
5. All figures are presented in Australian dollars, unadjusted for inflation.
11 ASX Announcement of 18 October 2019, “Muchea BFS and Maiden Ore Reserve”
Permitting
VRX is in the process of finalising further studies and compilation of necessary data to support
formal referrals to the Federal Department of Agriculture, Water and Environment (DAWE)
and the State Department of Water and Environmental Regulation (DWER) to secure
environmental approvals for the development of the Muchea Project. The Company and its
environmental consultants have held pre-referral meetings with representatives from DAWE
and DWER and received valuable feedback as to requirements for these referrals.
The Company will also seek to expedite approval for its mine plan and the issue of a mining
permit from the Department of Mines, Industry Regulation and Safety.
Potential for Extension of Life of Mine
Mining Lease M70/1390 is a conversion of part of Exploration Licence E70/4886, which covers
a portion of file notation area 12671 (FNA). The FNA ground within the Exploration Licence
sits adjacent to the Mining Lease and outside of the current proposed development area and
does not affect the BFS-modelled 25-year production life.
VRX intends to seek access to this ground to extend the Muchea Project’s mine life to well
beyond 25 years. To that end, the Company will continue to assess available options to do
so while addressing concerns relating to the FNA.
Aggregate Project Metrics
Key outcomes and summary financial model outputs for each individual project, and in
aggregate, from the BFSs for each project12 are set out below. The combined post-tax NPV10
of $727.8 million
Arrowsmith North Arrowsmith Central
Muchea
Total
Post Tax, ungeared NPV10
$242.3m
$147.6m
$337.9m
$727.8m
Post Tax, ungeared NPV20
$99.8m
$56.1m
$146.4m
$302.3m
Post Tax, ungeared IRR
79%
60%
96%
83%
Payback period (yrs) (post tax) (ramp up rate)
2.4
2.8
2.3
2.4
Exchange Rate US$/A$
$0.70
$0.70
$0.70
$0.70
Life of Mine (yrs) (Scope of BFS Study)
25
25
25
25
Total Sales (initial 25 years) no escalation
$2,773m
$2,167m
$3,345m
$8,285m
EBIT
$1,144m
$737m
$1,540m
$3,421m
Cashflow after finance and tax
$835m
$539m
$1,123m
$2,497m
Capex (2 mtpa)
$28.3m
$25.9m
$32.8m
$87m
Capex contingency (inc)
20%
20%
20%
20%
Life of Mine C1 costs, FOB Kwinana (inc royalties)
$30.18
$27.67
$32.74
$30.24
Tonnes Processed (initial 25 years) (Mt)
53
51
54
158
Production Target (Mt) (BFS Study) (initial 25 Years)
47.7
39.6
48.3
136
Probable Ore Reserves (Mt)
204
18.9
18.7
242
Ore Reserve life (yrs)
102
10
9-10
JORC Resources (million tonnes)
771
77
208
1,056
Notes:
1. A proportion of the production target for each of Arrowsmith Central and Muchea is based on Inferred Mineral
Resource. There is a low level of geological confidence associated with inferred mineral resources and there is no
certainty that further exploration work will result in the determination of indicated mineral resources or that the
production target itself will be realised.
2. The Ore Reserves and, in the case of Arrowsmith Central and Muchea, the Inferred Mineral Resource underpinning
the above production targets have been prepared by a Competent Person in accordance with the requirements of the
JORC Code.
3. Full summaries of economic assumptions are set out in the BFS for each project. All such material assumptions
continue to apply and have not materially changed from the dates of release of the BFSs.
4. All figures are presented in Australian dollars, unadjusted for inflation
12 ASX announcements of 28 August 2019, “Arrowsmith North BFS and Maiden Ore Reserve”,
17 September 2019, “Arrowsmith Central BFS and Maiden Ore Reserve” and
18 October 2019, “Muchea BFS and Maiden Ore Reserve”.
Biranup
On 1 July 2020, the Company announced it had entered into a conditional agreement with
New Energy Metals Limited (to be renamed Nickel X Limited) for the sale of its Biranup
Project and an IPO and listing of that company on the ASX.
Originally expected to complete by the end of 2020, increasing activity for new ASX listings
generally has delayed progress on the IPO. The Company has agreed a new completion
sunset date of 30 June 2021, subject to minimum exploration expenditure obligations being
satisfied by the purchaser in Q1 2021. The IPO is scheduled for completion in early 2021.
Corporate
On 20 November 2020 VRX Silica Limited announced that it has received binding commitments
for a capital raising via a share placement to institutional, professional and sophisticated
investors to raise $7 million before costs.
VRX received strong support for the capital raising from a wide range of investors, with bids
received well in excess of the amount raised.
This placement positioned VRX to rapidly advance the development of its silica sand projects,
in particular at Arrowsmith North for grade control drilling for the first 10 years of production,
confirmatory test work, drilling and equipping water bores, port access design, construction of
access roads and final engineering.
The placement was conducted at 18 cents per share, which represented a 23.4% discount to
the last closing price of VRX shares on ASX of 23.5 cents prior to announcing the placement
and a 13.6% discount to the 10-day VWAP of 20.8 cents as at the same date. A total of 38.9
million new shares were issued within the Company’s current placement capacity under Listing
Rule 7.1.
Funds raised under the placement are being allocated to pre-production preparatory work at
VRX’s Arrowsmith North Silica Sand Project, additional drilling at VRX’s Muchea and Boyatup
Silica Sand Projects, and general working capital.
Euroz Hartleys Limited (AFSL No 230052) acted as lead manager to the placement.
Specific disclosure required under GN23
Details of mining exploration activities
Details of exploration activities are set out above.
The exploration and evaluation expenditure expensed during the quarter included a refund of
tenement rent of $36,000 received upon the granting of Muchea mining lease M70/1390. The
$137,000 amount of exploration and evaluation expenditure capitalised is comprised of heritage
surveys ($35,000), metallurgical test work ($37,000), legal fees relating to mining lease
applications ($26,000), topographical surveys ($17,000), environmental approvals advice
($17,000) with the balance being sample assays and storage.
Details of mining production and development activities
No production and development activities were undertaken during the quarter.
Details of tenement activities
The tenement schedule on the following page shows all holdings and any change for the
Company and its subsidiaries.
During the quarter, the following tenements were granted:
Arrowsmith North Silica Sand Project
Mining Lease M70/1389
Miscellaneous Licence L70/208
Arrowsmith Silica Sand Central Project
Mining Lease M70/1392
Miscellaneous Licence L70/202
Miscellaneous Licence L70/203
Muchea Silica Sand Project
Mining Lease M70/1390
Exploration Licence E70/5651 (Muchea Project) was applied for during the quarter.
Details of related party payments
The aggregate amount of payments to related parties and their associates of $94,000
represents directors’ fees and salaries paid during the quarter.
This report has been authorised for release to ASX by the Board of Directors.
Further information:
Bruce Maluish
Managing Director
brucem@vrxsilica.com.au
0418 940 417
Andrew Rowell
Cannings Purple
arowell@canningspurple.com.au
0400 466 226
Material Assumptions
Full details of the bankable feasibility studies for the Arrowsmith North, Arrowsmith Central
and Muchea Silica Sand Projects, including material assumptions, are contained in VRX’s
ASX announcements of 28 August 2019, 17 September 2019 and 18 October 2019,
respectively. All such material assumptions continue to apply and have not materially changed
from the date of release of the BFSs. Whilst VRX considers all of the material assumptions to
be based on reasonable grounds, there is no certainty that they will be correct or that the
range of outcomes indicated within the studies will be achieved.
Competent Persons’ Statements
The information in this document that relates to Arrowsmith North, Arrowsmith Central and
Muchea Exploration Results and Muchea Aircore Drilling Area Mineral Resources are based
on data collected and compiled under the supervision of Mr David Reid, who is a full-time
employee of VRX Silica. Mr Reid, BSc (Geology), is a registered member of the Australian
Institute of Geoscientists and has sufficient experience that is relevant to the style of
mineralisation and type of deposit under consideration and the activity being undertaken to
qualify as a Competent Person under the 2012 edition of the Australasian Code for Reporting
of Exploration Results, Mineral Resources and Ore Reserves (JORC Code). Mr Reid consents
to the inclusion of the data in the form and context in which it appears.
The information in this document that relates to Arrowsmith North, Arrowsmith Central and
Muchea Auger area Mineral Resources is based on information compiled by Mr Grant Louw
who was a full-time employee of CSA Global, under the direction and supervision of Dr Andrew
Scogings, who is an Associate of CSA Global. Dr Scogings is a Member of the Australasian
Institute of Mining and Metallurgy and a Member of the Australian Institute of Geoscientists.
He is a Registered Professional Geologist in Industrial Minerals. Dr Scogings has sufficient
experience relevant to the style of mineralisation and type of deposit under consideration and
to the activity which he is undertaking to qualify as Competent Person as defined in the 2012
edition of the Australasian Code for the Reporting of Exploration Results, Mineral Resources,
and Ore Reserves (JORC