Quarterly Activities/Appendix 5B Cash Flow Report
Released
Released
Announcement PDF
ASX Announcement
20 January 2026
December 2025 Quarterly Activities Report
Highlights:
Six binding offtake contracts signed with
customers in South Korea, Taiwan, the
Philippines and China
Offtake customers are well-established,
reputable and substantial suppliers into the
foundry, glassmaking and filter industries
Aggregate 960,000tpa committed, close to
Arrowsmith North’s target start-up capacity,
with further offtakes anticipated
Contract to purchase Arramall farm site,
adjacent to Arrowsmith North
Implementation of succession plan and new
CEO appointment
Pareto Securities appointed as manager for
Arrowsmith North debt financing
Equity capital raising of $2.1m (before costs)
Arrowsmith North is recognised as a
globally significant, high-quality and long-
life silica sand project for foundry and glass
markets in Asia
VRX Silica Limited (VRX or Company) is pleased to provide
this activities report for the December 2025 quarter.
Arrowsmith North Silica Sand Project
VRX’s 100%-owned Arrowsmith North Silica Sand Project,
located approximately 270km north of Perth, hosts a globally
significant deposit of high-quality silica sand.
The project is underpinned by a JORC-compliant Proved and
Probable Ore Reserve of 221Mt at 99.5% SiO₂, supporting
the potential for long-term production into the foundry,
container glass and flat-glass markets, primarily servicing
growing demand in Asia.
Arrowsmith North has the potential to establish a new, long-
term silica sand industry in Western Australia, delivering
substantial economic benefits to the State and the Mid West
region. These benefits include sustained direct and indirect
employment, royalties, and regional economic development.
ASX: VRX
Capital Structure
Shares on Issue:
778.3 million
Options on issue:
33.7 million
Corporate Directory
Paul Boyatzis
Non-Executive Chairman
Bruce Maluish
Managing Director
Peter Pawlowitsch
Non-Executive Director
David Welch
Non-Executive Director
Ian Hobson
Company Secretary
Silica Sand Projects
Arrowsmith Silica Sand
Projects, 270km north of
Perth, WA.
Muchea Silica Sand
Project, 50km north of
Perth, WA.
Boyatup Silica Sand
Project, 100km east of
Esperance, WA.
The Company is actively
assessing other silica sand
and downstream
processing projects in
Australia.
2
The project has strong support from key stakeholders, including local Traditional Owner
groups, local shires, the Mid West Development Commission, the Mid West Chamber of
Commerce and Industry, and both State and Federal Governments. Economic studies
demonstrate robust project metrics across a range of silica sand products.
Globally, the silica sand market continues to experience strong growth, driven by increasing
demand from the construction sector — particularly flat glass used in residential and
commercial buildings — and rising consumption of automotive glass in Asia’s expanding
automotive industry. The foundry sector is also exhibiting strong growth, supported by
increasing demand in established markets such as South Korea, Japan and China, as well as
emerging markets including Thailand and India, against a backdrop of industry-wide
expansion and tightening supply across Asia.
Australia is currently the largest exporter of silica sand in the Asia-Pacific region, with exports
dominated by multinational producers. Total exports exceeded 2.3 million tonnes in the
previous year.
Binding Offtake Contracts Signed for Arrowsmith North
During the quarter, VRX secured six binding offtake agreements for the supply of silica sand
from Arrowsmith North. The contracts provide for the supply of an aggregate minimum of
approximately 960,000 tonnes per annum of high-quality silica sand products to established
and reputable customers supplying the foundry and glassmaking industries across Asia. The
customer base comprises two major suppliers into the South Korean foundry sector, a leading
supplier of foundry, glassmaking, water filtration media and sized dry sand in Taiwan, a glass
manufacturer supplier in the Philippines, and two glass manufacturing and foundry suppliers
in China. Collectively, these customers are recognised suppliers to the Asian foundry and
glassmaking markets. See ASX releases dated 23 October and 11 December 2025.
VRX plans to progressively ramp up production at Arrowsmith North from an initial production
rate of approximately 1 million tonnes per annum (Mtpa) to more than 2 Mtpa, supporting an
operating life of several decades. The aggregate contracted volumes under the binding offtake
agreements broadly align with the proposed initial production capacity at project
commencement.
The Company is continuing discussions with additional prospective customers and is
negotiating further binding offtake agreements.
The execution of these binding offtake agreements provides increased certainty in relation to
sales volumes and revenue generation and represents an important milestone in supporting
engagement with potential debt financiers.
Purchase of Arramall Farm Site
During the quarter, the Company announced that it had entered into a conditional binding
contract to purchase the Arramall farm site, which sits on freehold land adjacent to Arrowsmith
North. See ASX release dated 29 October 2025. Comprising approximately 2,091 hectares
over two separate lots, Arramall contains tracts of both cleared land and native vegetation,
bordered to the east by the Company’s mining lease at Arrowsmith North and to the west by
Brand Highway.
The site is suitable for locating the proposed silica sand processing plant and associated
infrastructure for Arrowsmith North with easy access to Brand Highway for transportation of
products to Geraldton Port. The site is also highly suited for locating a solar farm and a
potential future renewable power solution for Arrowsmith North.
3
The contract provides for the purchase from an unrelated party with the purchase price within
the range for capital expenditure on land acquisitions for the project provided for in the
Company’s financial model for Arrowsmith North, and it is proposed that the site will form part
of the Company’s overall environmental offset strategy for the project.
Preliminary work undertaken by VRX on Arramall indicates that, given the site’s location, there
are likely to be significant cost savings for the Company both in the construction phase and
once in production, based on the Company’s financial modelling for Arrowsmith North. Further
and detailed due diligence was undertaken during the quarter to determine the extent of these
savings. In addition, locating the plant on cleared, freehold land close to Brand Highway will
reduce the overall environmental impact of Arrowsmith North as less native vegetation will be
disturbed both for the plant and roads to the highway.
During the quarter the Company completed a number of targeted environmental and technical
surveys required to support the relocation of the processing plant from its originally approved
location within the Arrowsmith North Mine Development Envelope (MDE) and environmental
offset strategy.
The surveys included flora mapping, vegetation assessments and targeted orchid studies
associated with a proposed new access road. Additional vegetation studies were also
undertaken for an alternative access road alignment and a northern extension to the MDE.
Vegetation mapping was completed for the proposed alternative offset site, including a
Carnaby’s Cockatoo habitat assessment. Technical surveys include detailed imaging and
topography and geotechnical testing on the plant site.
In September 2025, VRX received State environmental approval for the Arrowsmith North
Project, with the Western Australian Minister for the Environment, the Hon Matthew Swinbourn
MLC, approving the development through the issue of a Statement that a Proposal May Be
Implemented. This approval followed an appeal process and confirmation that the Minister
had determined the Environmental Protection Authority of Western Australia’s (EPA)
assessment to be adequate and that no further assessment was required.
The State environmental approval includes conditions relating to staged mining, achievement
of specified environmental outcomes, rehabilitation, and ongoing monitoring and reporting.
These conditions were previously agreed and are consistent with VRX’s commitment to safe,
sustainable and responsible operations at Arrowsmith North.
VRX will lodge an amendment application with the EPA this quarter to relocate the processing
plant and access road. The revised layout significantly reduces permanent clearing, affects
substantially fewer priority species, and provides scope to lower emissions through the
incorporation of a solar farm to be developed on previously cleared land within the Arramall
farm site. The amendment represents a substantial reduction in environmental impact and is
not expected to materially affect timing for commencement of project construction. During the
quarter, the Company also engaged with the Federal environmental agency, the Department
of Climate Change, Energy, the Environment and Water, for approval of the revised offset
strategy. This separate process will run in parallel with the EPA amendment process during
the current quarter.
The contract to purchase the Arramall farm site is conditional on VRX and its advisers
completing detailed due diligence on the site and its suitability for the project, including
satisfying the requirements of all relevant government authorities, and the VRX Board of
Directors approving a final investment decision (FID) for the project, each within six months.
Subject to satisfaction or waiver of those conditions, settlement is to occur within three months
thereafter. The contract is otherwise on standard terms and conditions for a transaction of this
nature.
4
Implementation of succession plan and new CEO appointment
During the quarter, VRX announced the implementation of a succession plan in relation to the
chief executive role at the Company and appointment of Tony Swiericzuk as new Chief
Executive Officer. See ASX release dated 23 December 2025.
Following discussions during the quarter between the Board and Managing Director, Bruce
Maluish, around succession planning for the chief executive role and Mr Maluish indicating
that he was unlikely to remain in his current role for the long term, the Board commenced a
strategic exercise to allow for an orderly transition to new leadership as the Company
progresses development of Arrowsmith North.
Mr Swiericzuk is a seasoned mining executive with over 30 years of leadership experience
and a distinguished career including in large scale mines and bulk ports. He brings strong
expertise in mining operations, exploration, project development, contractor management,
sales and marketing, and financing, along with a strong track record of engaging with Federal,
State, Local, and First Nation authorities. His deep industry knowledge spans exploration,
construction, mining, bulk ports, and manufacturing, providing him with a comprehensive, end-
to-end supply chain perspective. As general manager of the Christmas Creek Mine for FMG,
he oversaw the construction, commissioning and ramp-up of this project from 15Mtpa to
60Mtpa, then proceeded to optimise the operation and help drive FMG to become the world’s
lowest cost iron ore producer.
Mr Swiericzuk will commence with the Company on 1 February 2026 on a part-time basis as
he winds down his current engagements and will commence in the CEO role on a full-time
basis by 1 July 2026. Mr Maluish will remain with the Company as Managing Director during
this interim period and will phase out of that role into a Non-Executive Director role during that
time.
Project Finance for Arrowsmith North – Debt Proposals Received
During the quarter, VRX mandated Argonaut PCF to act as the Company’s financial adviser
in connection with potential debt financing for Arrowsmith North. See ASX release dated 11
December 2025.
An independent technical review of the project was completed during the quarter and will form
a key component of financiers’ due diligence when assessing potential support for the project’s
development.
Following the granting of key project approvals, interest from potential debt financiers has
increased materially and a formal process was initiated during the quarter.
VRX then appointed international investment bank and debt capital markets specialist Pareto
Securities as Manager for fixed income debt financing to support construction of the
Arrowsmith North project. The appointment followed a competitive selection process and
reflects the strong level of interest in the project.
The Company looks forward to working with Pareto and its financial adviser, Argonaut, to
advance the debt financing process during the current quarter.
Equity Placement
VRX conducted an equity capital raising from sophisticated professional investors of
$2.1 million (before costs) under a placement of fully paid ordinary shares (Placement).
The Placement comprised an issue of approximately 28.5 million new shares equating to
approximately $2.05 million within the Company’s placement capacity under ASX Listing Rule
5
7.1 and a conditional placement of approximately 0.7 million new shares equating to
approximately $50,000 to VRX Directors subject to obtaining shareholder approval at a future
general meeting.
The Placement was supported by existing shareholders and new institutional investors.
Unified Capital Partners Pty Ltd acted as sole lead manager and bookrunner to the Placement.
Mining and Logistics Contracts for Arrowsmith North in Progress
During the quarter VRX continued progress on all infrastructure agreements relating to the
development of Arrowmsith North including port logistics, transport, mining services, power
supply and construction contracts. These are expected to be concluded in the current quarter.
ASX Listing Rule 5.3 Disclosures
Details of mining exploration activities:
Payments for exploration & evaluation under operating activities of $260,000 related mainly to
tenement rents and rates.
Payments for exploration & evaluation under investing activities of $213,000 consists mainly
of environmental surveys and approval costs.
There were no substantive mining production and development activities during the quarter.
Details of tenement activities:
During the quarter, Exploration Licence E70/6765 was applied for.
Details of related party payments:
The aggregate amount of payments to related parties and their associates of $134,000
represents directors’ fees and salaries paid during the quarter.
This quarterly activities report has been approved for release by the Managing Director.
Further information:
Bruce Maluish Peter Klinger
Managing Director Purple
brucem@vrxsilica.com.au pklinger@purple.au
0418 940 417 0411 251 540
6
Combined 1.4Bn tonne Mineral Resource
Table 1 Mineral Resource Statement (as at 31 December 2025)
Project Classification Mt
SiO₂
%
Al₂O₃
%
Fe₂O₃
%
TiO₂
%
LOI
%
Muchea
Indicated 29 99.6 0.1 0.03 0.1 0.2
Inferred 179 99.6 0.1 0.02 0.1 0.2
Total 208 99.6 0.1 0.02 0.1 0.2
Arrowsmith
North
Measured 10 95.9 1.9 0.7 0.3 0.7
Indicated 237 97.7 1.0 0.4 0.2 0.5
Inferred 266 98.4 0.7 0.3 0.2 0.4
Total 513 98.0 0.9 0.3 0.2 0.4
Arrowsmith
Brand
Inferred 523 97.3 1.4 0.4 0.2 0.6
Total 523 97.3 1.4 0.4 0.2 0.6
Arrowsmith
Central
Indicated 28.2 96.6 1.7 0.4 0.2 0.7
Inferred 48.3 96.9 1.5 0.4 0.2 0.7
Total 76.5 96.8 1.5 0.4 0.2 0.7
Boyatup
Inferred 60 97.8 0.8 0.2 0.1 0.9
Total 60 97.8 0.8 0.2 0.1 0.9
Total Mineral Resource 1,381 Million Tonnes
Table 2 Ore Reserve Statement (as at 31 December 2025)
Project Classification Product Mt
SiO2
%
Al2O3
%
Fe2O3
%
TiO2
%
LOI
%
Muchea Probable
F80 10.2
99.9 0.02 0.008 0.03 0.1
F80C 4.25
F150 4.25 99.8 0.07 0.015 0.035 0.1
Muchea Ore Reserve 18.7 Million Tonnes
Arrowsmith
North
Proved
AFS20 0.8 99.5 0.25 0.07 0.05 0.1
AFS35 3.9 99.5 0.5 0.06 0.05 0.1
AFS55 2.7 99.2 0.5 0.1 0.05 0.1
Local 1.8
Proved Ore Reserve 9.2 Million Tonnes
Probable
AFS20 24.2 99.5 0.25 0.07 0.05 0.1
AFS35 102.5 99.5 0.5 0.06 0.05 0.1
AFS55 51.1 99.2 0.5 0.1 0.05 0.1
Local 34.1
Probable Ore Reserve 212 Million Tonnes
Arrowsmith North Ore Reserve 221 Million Tonnes
Arrowsmith
Central
Probable
CF400 4.2
99.6 0.25 0.04 0.03 0.1
C20 8.4
C40 4.2
High TiO2 2.2 <1% 2%
Arrowsmith Central Ore Reserve 18.9 Million Tonnes
Total Ore Reserve 259 Million Tonnes
7
Compliance Statement
The information in this document that relates to the estimation and reporting of the Mineral
Resource and Ore Reserves for the Company’s silica sand projects is extracted from releases
to ASX on 28 August 2019,11 November 2022 and 6 March 2024 (Arrowsmith North), 17
September 2019 (Arrowsmith Central), 9 May 2023 (Arrowsmith Brand), 18 October 2019
(Muchea) and Boyatup (18 August 2022). The Company confirms that it is not aware of any
new information or data that materially affects the information included in this document and
all material assumptions and technical parameters underpinning the estimates continue to
apply and have not materially changed.
The information in this document that relates to the Company’s production target for the
Arrowsmith North silica sand project is extracted from releases to ASX on 6 March 2024. The
Company confirms that it is not aware of any new information or data that materially affects the
information included in this document and all material assumptions underpinning the production
target continue to apply and have not materially changed.
The information in this announcement that relates to the previous exploration results have
been cross referenced to the original announcement. The Company is not aware of any new
information or data that materially affects the previous exploration results.
The Company confirms that the form and context in which the Competent Persons’ findings
are presented have not been materially modified.
8
Interests in Mining Tenements (Western Australia)
Arrowsmith Project – Silica Sand
Tenement Status
Interest at
beginning of
quarter
Interests relinquished,
reduced or lapsed
Interests acquired
or increased
Interest at end
of quarter
E70/5027 Granted 100% - - 100%
E70/5817 Granted 100% - - 100%
E70/6765 Application - - - -
M70/1389 Granted 100% - - 100%
R70/64 Granted 100% - - 100%
R70/65 Granted 100% - - 100%
L70/202 Granted 100% - - 100%
L70/203 Granted 100% - - 100%
L70/208 Granted 100% - - 100%
L70/229 Application - - - -
L70/230 Granted 100% - - 100%
G70/264 Granted 100% - - 100%
G70/265 Granted 100% - - 100%
Muchea Project – Silica Sand
Tenement Status
Interest at
beginning of
quarter
Interests relinquished,
reduced or lapsed
Interests acquired
or increased
Interest at end
of quarter
E70/4886 Granted 100% - - 100%
E70/5651 Application - - - -
M70/1390 Granted 100% - - 100%
M70/1414 Application - - - -
L70/204 Granted 100% - - 100%
L70/205 Application - - - -
L70/206 Granted 100% - - 100%
Boyatup Project – Silica Sand
Tenement Status
Interest at
beginning of
quarter
Interests relinquished,
reduced or lapsed
Interests acquired
or increased
Interest at end
of quarter
E69/3560 Retention 100% - - 100%
9
About VRX’s target silica sand markets
Foundry
Silica sand is an essential part of both the ferrous and non-ferrous foundry industries. Metal
parts ranging from engine blocks to sink faucets are cast in a sand-and-clay mould to produce
their external shape, often using a resin coat to create the desired internal shape. Silica’s high
fusion point (1,760°C) and low rate of thermal expansion produce stable cores and moulds
compatible with all pouring temperatures. Its chemical purity also helps prevent interaction
with catalysts or affecting the curing rate of chemical binders, for that reason, customers are
looking for high quality silica sand that meets their specifications for size and shape.
Another critical specification is the hardness of silica grains to deliver the required crush
resistance to high pressure from molten metals.
Arrowsmith North is capable of producing multiple high quality sand products for the foundry
industry as confirmed by potential offtake partners in Asia following extensive testwork.
Glassmaking
Silica sand is the primary component of all types of standard and specialty glass. It provides
the essential SiO2 component of glass formulation and its chemical purity is the primary
determinant of colour, clarity and strength in glass. Silica sand is used to produce flat glass
for building and automotive use, container glass for foods and beverages, and tableware. In
its pulverised form, ground silica is required in the production of fibreglass insulation and for
reinforcing glass fibres. Specialty glass applications include test tubes and other scientific
tools, incandescent and fluorescent lamps, television and computer LCD/LED monitors.
Glassmaking physical specifications focus on particle size, as it significantly impacts melting
efficiency. Uniform grain size is preferred to reduce energy use and ensure complete melting.
In fibreglass production, over 99.5% of raw material grains are smaller than 0.045 mm (45μm),
and tighter limits are being considered. Coarse particles are hardest to melt and can cause
defects. Grain shape also matters—if too many grains are coarser than specified, incomplete
melting and poor product quality can result.
Refractory heavy minerals (RHM)—such as iron, zircon, corundum, chrome spinels, rutile, and
staurolite—should generally be avoided in glassmaking because they do not melt at standard
glass-making temperatures. This leads to solid inclusions or defects ("stones") in the final
glass. Limits on RHM are typically based on their size and amount, with particles larger than
0.25 mm (10 mesh) being the most problematic. These may be restricted by weight
percentage or particle count.
10
About VRX Silica Limited
VRX Silica Limited (ASX: VRX) is the most advanced pureplay silica sand company listed
on the ASX, developing its 100% owned silica sand projects at Arrowsmith (North, Brand
and Central), Muchea and Boyatup in Western Australia.
Silica sand is the most used commodity on the planet after air and water. It is the main
ingredient in foundry casting and in all types of glassmaking, including specialty solar panel
and high-tech glass. It is a finite resource that is running out, with the Asia-Pacific region
experiencing an ever-growing supply shortfall that will drive up prices in the long term.
VRX has significant Resources to underpin very long-life silica sand projects.
Arrowsmith is located 270km
north of Perth. Arrowsmith
North boasts a minimum 25-
year mine life capable of
producing more than 2Mt
tonnes per year of high-grade
(99.7% SiO2)* silica sand for
export to the foundry, container
glass and flat glass markets in
Asia, with permitting well
advanced, and will lead
production.
Muchea, located 50km north of
Perth, is an ultra-high-grade
(99.9% SiO2)* silica sand
project capable of producing
sand required for ultra-clear
glass for solar panels and other
high-tech glass applications.
Boyatup, located 100km east of
Esperance, is under
development and capable of
producing sand for the glass
market.
*Information relating to grades are extracted from releases to ASX on 28 August 2019, 11 November 2022 and 6
March 2024 (Arrowsmith North) and 18 October 2019 (Muchea). The company is not aware of any new information
or data that materially affects this information.
Rule 5.5
ASX Listing Rules Appendix 5B (17/07/20) Page 1
+ See chapter 19 of the ASX Listing Rules for defined terms.
Appendix 5B
Mining exploration entity or oil and gas exploration entity
quarterly cash flow report
Name of entity
VRX SILICA LTD
ABN Quarter ended (“current quarter”)
59 142 014 873 31 December 2025
Consolidated statement of cash flows
Current quarter
$A’000
Year to date
(6 months)
$A’000
1. Cash flows from operating activities
- -
1.1 Receipts from customers
1.2 Payments for
(260) (280)
(a) exploration & evaluation
(b) development - -
(c) production - -
(d) staff costs (349) (687)
(e) administration and corporate costs (466) (880)
1.3 Dividends received (see note 3) - -
1.4 Interest received 24 47
1.5 Interest and other costs of finance paid (on
lease liability)
(4) (8)
1.6 Income taxes paid - -
1.7 Government grants and tax incentives - -
1.8 Other (provide details if material) - -
1.9 Net cash from / (used in) operating
activities
(1,055) (1,808)
2. Cash flows from investing activities
- -
2.1 Payments to acquire or for:
(a) entities
(b) tenements - -
(c) property, plant and equipment (50) (50)
(d) exploration & evaluation (213) (291)
(e) investments - -
(f) other non-current assets - -
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
ASX Listing Rules Appendix 5B (17/07/20) Page 2
+ See chapter 19 of the ASX Listing Rules for defined terms.
Consolidated statement of cash flows
Current quarter
$A’000
Year to date
(6 months)
$A’000
2.2 Proceeds from the disposal of:
- -
(a) entities
(b) tenements - -
(c) property, plant and equipment - -
(d) investments - -
(e) other non-current assets - -
2.3 Cash flows from loans to other entities - -
2.4 Dividends received (see note 3) - -
2.5 Other (bonds deposit) - -
2.6 Net cash from / (used in) investing
activities
(263) (341)
3. Cash flows from financing activities
2,050 2,050
3.1 Proceeds from issues of equity securities
(excluding convertible debt securities)
3.2 Proceeds from issue of convertible debt
securities
- -
3.3 Proceeds from exercise of options - 4
3.4 Transaction costs related to issues of equity
securities or convertible debt securities
(105) (105)
3.5 Proceeds from borrowings - -
3.6 Repayment of borrowings - -
3.7 Transaction costs related to loans and
borrowings
- -
3.8 Dividends paid - -
3.9 Other (repayment of lease liability) (24) (48)
3.10 Net cash from / (used in) financing
activities
1,921 1,901
4. Net increase / (decrease) in cash and
cash equivalents for the period
4.1 Cash and cash equivalents at beginning of
period
3,252 4,103
4.2 Net cash from / (used in) operating
activities (item 1.9 above)
(1,055) (1,808)
4.3 Net cash from / (used in) investing activities
(item 2.6 above)
(263) (341)
4.4 Net cash from / (used in) financing activities
(item 3.10 above)
1,921 1,901
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
ASX Listing Rules Appendix 5B (17/07/20) Page 3
+ See chapter 19 of the ASX Listing Rules for defined terms.
Consolidated statement of cash flows
Current quarter
$A’000
Year to date
(6 months)
$A’000
4.5 Effect of movement in exchange rates on
cash held
- -
4.6 Cash and cash equivalents at end of
period
3,855 3,855
5. Reconciliation of cash and cash
equivalents
at the end of the quarter (as shown in the
consolidated statement of cash flows) to the
related items in the accounts
Current quarter
$A’000
Previous quarter
$A’000
5.1 Bank balances 3,855 1,252
5.2 Call deposits - 2,000
5.3 Bank overdrafts - -
5.4 Other (provide details) - -
5.5 Cash and cash equivalents at end of
quarter (should equal item 4.6 above)
3,855 3,252
6. Payments to related parties of the entity and their
associates
Current quarter
$A'000
6.1 Aggregate amount of payments to related parties and their
associates included in item 1
134
6.2 Aggregate amount of payments to related parties and their
associates included in item 2
-
Note: if any amounts are shown in items 6.1 or 6.2, your quarterly activity report must include a description of, and an
explanation for, such payments.
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
ASX Listing Rules Appendix 5B (17/07/20) Page 4
+ See chapter 19 of the ASX Listing Rules for defined terms.
7. Financing facilities
Note: the term “facility’ includes all forms of financing
arrangements available to the entity.
Add notes as necessary for an understanding of the
sources of finance available to the entity.
Total facility
amount at quarter
end
$A’000
Amount drawn at
quarter end
$A’000
7.1 Loan facilities - -
7.2 Credit standby arrangements - -
7.3 Other (please specify) - -
7.4 Total financing facilities - -
7.5 Unused financing facilities available at quarter end -
7.6 Include in the box below a description of each facility above, including the lender, interest
rate, maturity date and whether it is secured or unsecured. If any additional financing
facilities have been entered into or are proposed to be entered into after quarter end,
include a note providing details of those facilities as well.
8. Estimated cash available for future operating activities $A’000
8.1 Net cash from / (used in) operating activities (item 1.9) (1,055)
8.2 (Payments for exploration & evaluation classified as investing
activities) (item 2.1(d))
(213)
8.3 Total relevant outgoings (item 8.1 + item 8.2) (1,268)
8.4 Cash and cash equivalents at quarter end (item 4.6) 3,855
8.5 Unused finance facilities available at quarter end (item 7.5) -
8.6 Total available funding (item 8.4 + item 8.5) 3,855
8.7 Estimated quarters of funding available (item 8.6 divided by
item 8.3)
3.04
Note: if the entity has reported positive relevant outgoings (ie a net cash inflow) in item 8.3, answer item 8.7 as “N/A”.
Otherwise, a figure for the estimated quarters of funding available must be included in item 8.7.
8.8 If item 8.7 is less than 2 quarters, please provide answers to the following questions:
8.8.1 Does the entity expect that it will continue to have the current level of net operating
cash flows for the time being and, if not, why not?
Answer: Not applicable
8.8.2 Has the entity taken any steps, or does it propose to take any steps, to raise further
cash to fund its operations and, if so, what are those steps and how likely does it
believe that they will be successful?
Answer: Not applicable
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
ASX Listing Rules Appendix