Arrowsmith Silica Sands Project Testwork
Released
Released
Announcement PDF
30 January 2018
ASX ANNOUNCEMENT
Arrowsmith Silica Sands Project Testwork
Glass-making quality with low capital intensity
Conventional processing
Potential for higher quality
Ventnor Resources Ltd (“Ventnor” or “the Company”) (ASX: VRX) is
pleased to announce the results of an initial testwork program on
samples from its Arrowsmith Silica Sands Project, located 270km
north of Perth, Western Australia.
Ventnor has four exploration license applications pending totaling
2
400km and holding significant sand deposits.
The project is adjacent to Brand Highway and a rail connection to
Geraldton Port, suitable for bulk handling.
Ventnor has been able to conduct a shallow hand auger program to
collect composite representative samples from the Arrowsmith North
prospect.
Samples were submitted to Nagrom Laboratories for an initial
testwork program, which would emulate conventional sand
processing techniques.
This testwork confirms that processing to upgrade the sand to glassmaking quality will have a low-capital intensity, low technical risk and
requires no processing chemicals.
Further testwork programs will be undertaken to investigate
processing options to higher quality and higher value products.
Ventnor has been investigating markets in the Asia-Pacific region
this year to potentially supply sand used for glass manufacturing,
concrete construction and as a tech metal.
Asian glass demand is increasing for energy-saving double glazing
and other applications within the expanding automobile industry in
China and India.
There is a looming supply shortage because of reducing access to
coastal and river deposits, depletion of known deposits and
restrictions due to environmental regulation.
The Arrowsmith area potentially has low environmental impact
mining propositions; rehabilitation techniques are well established in
the industry.
Managing Director Bruce Maluish said: “This initial program
demonstrates that the Arrowsmith sand can easily achieve
glassmaking quality and potentially a much higher quality and
valuable product using conventional sand processing techniques”.
“Further testwork will be undertaken to determine final circuit design
and products,” Mr Maluish said.
ASX: VRX
Capital Structure
Shares on Issue 251 million
Unlisted Options 21.25
million
Market Cap @ 6¢ a share
$15 million
Cash $1.2M
Corporate Directory
Paul Boyatzis
Non-Executive Chairman
Bruce Maluish
Managing Director
Peter Pawlowitsch
Non-Executive Director
John Geary
Company Secretary
Company Projects
Arrowsmith silica sands
project near Eneabba, WA.
Biranup base metals and
gold project adjacent to the
Tropicana Gold Mine, WA.
Warrawanda nickel Project
south of Newman, WA.
Arrowsmith Project Location
Arrowsmith Testwork Update
On 14 December 2017, Ventnor announced a mapping and shallow hand auger sampling
program was under way at its Arrowsmith Project, 270km north of Perth in Western Australia,
Also announced were preliminary testwork results, which indicated the bulk sand could be
upgraded using simple sizing techniques, with further testwork to be carried out to determine
if the sand could be further upgraded. In addition to this, samples were to be prepared and
sent for proppant testing to API RP-19C standards.
The results of the auger sampling completed in December remain outstanding because of
Laboratory delays. The results are now scheduled to be received next month. The proppant
testing is well advanced and results are expected in the coming weeks.
The results of further silica sand testwork have been received and are summarised below.
A 5kg composite from Arrowsmith North was tested at the Nagrom Laboratory in Kelmscott, in
Perth, using the following flowchart:
Nagrom Silica Sand Testwork
Head assay Arrowsmith Nth Composite
plus mass balance throughout
~5kg
Dry Bulk Density
Attrition 25-30%
10 Mins
Assay
Assay
Assay
Assay both mag and non-mag
Assay
Assay
Seive Separation
<0.212mm
0.212mm - 1.18mm
+1.18mm
Magnetic Separation of
Product @ 14,000 gauss
Product
Non-mag is Product
Seive Separation Non-mag
Product (0.85mm-0.425mm)
Product (0.425-0.212mm)
On the page following is a table detailing the testwork results. The feed stock in the test had a
head assay of 97.7% SiO2 +LOI1000C, after attritioning, magnetic separation and sizing, the
0.425mm - 0.85mm product achieved a grade of 99.5% SiO2 +LOI1000C. The remainder of the
product, 0.212mm - 0.425mm, returned an assay of 99.3% SiO2 +LOI1000C. It is believed that
additional testwork will improve both of these product grades.
Of significance is the mass balance achieved during testing, as this is an indication of the
potential recovery from the in-situ resources. From the feed stock, 93.6% is recovered in the
initial 0.12mm – 1.18mm sizing and passed on for attritioning and magnetic separation. With
negligible mass loss in the magnetic separation and final sizing step, the potential product
recovery is +93%. The higher grade 0.425mm - 0.85mm sizing constitutes 70% of the final
product with the finer 0.212mm - 0.425mm, sizing making up the balance.
In addition to the testwork completed by Nagrom, Scanning Electron Microscopy (SEM) and
Qualitative X-ray Diffraction (XRD) work has been completed by Microanalysis in East Perth
to better understand the mineral forms of the deleterious elements. An understanding of the
minerals that are present in the bulk sand mass will aid in further upgrading of the final
product.
This work has resulted in the following findings:
The Loss on Ignition (LOI1000C) is largely because the presence of salts such as
Halite and Sylvite;
The Fe and Ti minerals are present as Iron oxides, Ilmenite and Rutile;
Aluminium, a major contaminant, is present as Al(OH)3, being a form of bauxite such
as Gibbsite; and
Mineral grains are largely liberated, with 60-78% for the Fe and Ti minerals, and
99.8% for the Gibbsite.
Future Testwork
The next phase of planned testwork focused on the removal of the dense Fe/Ti minerals,
>4g/cc, and the lighter Gibbsite, <2.4g/cc, in comparison with the quartz sand grains,
2.62g/cc. Initial testing using Heavy Liquid Separation (HLS) will be followed with a bulk
sample, ~200kg, to be tested over a wet table to determine if conventional gravity separation
equipment such as spirals will assist with the final product upgrade. Testwork to date shows
that ~5,000ppm, or 0.5% of the current product, is reporting to these minerals. Successful
gravity separation could upgrade the final product to >99.8% SiO2 +LOI1000C.
It is anticipated the bulk sample product will be used for marketing purposes to secure offtake
and pricing agreements.
Further information:
Bruce Maluish
Managing Director
Ventnor Resources
0418 940 417
Andrew Rowell
Cannings Purple
arowell@canningspurple.com.au
0400 466 226
Competent Person’s Statement
The information in this release that relates to Exploration Results is based on, and fairly represents,
information compiled by Mr David Reid who is a Member of the Australian Institute of Geoscientists
(MAIG). Mr Reid is a contractor to Ventnor Resources Limited. Mr Reid has sufficient experience
which is relevant to the style of mineralisation and type of deposit under consideration and to the
activity which he is undertaking to qualify as a Competent Person as defined in the “2012 Edition of
the Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves.”
Mr Reid consents to the inclusion in this report of the matters based on information provided by him
and in the form and context in which it appears.
About Ventnor
Ventnor Resources Ltd (“Ventnor”) (ASX: VRX) has four exploration licence applications pending over
the Arrowsmith Silica Sands Project, located 270km north of Perth, Western Australia. Initial testwork is
focusing on confirming that the sand can be upgraded to glass-making quality.
Ventnor also has granted tenements adjacent to the Tropicana Gold Mine in WA that are prospective
for gold and base metals (Biranup Project), with prospects identified following an extensive review of
historical data. The Company has compiled an extensive database of historic exploration, conducted
extensive MLEM surveys in the region, and completed initial drill programs at a number of its prospects.
Ventnor has an extensive landholding prospective for silica sand at the Arrowsmith Project as detailed in
a previous announcement.
Also in Western Australia, 40km south of Newman, is Ventnor’s Warrawanda Nickel Project, which is
prospective for nickel sulphides.
Proven Management
The Ventnor directors have extensive experience in mineral exploration and production, and in the
management of publicly listed mining and exploration companies.