Quarterly Activities/Appendix 5B Cash Flow Report
Released
Released
Announcement PDF
ASX Announcement
30 January 2025
December 2024 Quarterly Activities Report
Highlights:
EPA site visit to Arrowsmith North and
presentation to EPA Board
EPA accepts and publishes Arrowsmith
North Response to Submissions
EPA finalises assessment report for
Arrowsmith North and recommends
approval to Minister for Environment
Offtake interest under term sheets for
Arrowsmith North increases to
640,000 tonnes per annum
Capital raising of $5 million
VRX Silica Limited (VRX or Company) is pleased to provide
this activities report for the December 2024 quarter.
Arrowsmith North Environmental Approval
VRX has continued to focus on progressing approvals for
the development of the Company’s 100% owned Arrowsmith
North Silica Sand Project, approximately 270km north of
Perth in Western Australia, culminating subsequent to the
end of the quarter in the Environmental Protection Authority
of Western Australia (EPA) finalising its assessment report
for Arrowsmith North and recommending the approval of the
proposal to the Minister for Environment.
ASX: VRX
Capital Structure
Shares on Issue:
744 million
Listed Options:
56 million
Unlisted Options:
35 million
Corporate Directory
Paul Boyatzis
Non-Executive Chairman
Bruce Maluish
Managing Director
Peter Pawlowitsch
Non-Executive Director
David Welch
Non-Executive Director
Ian Hobson
Company Secretary
Silica Sand Projects
Arrowsmith Silica Sand
Projects, 270km north of
Perth, WA.
Muchea Silica Sand
Project, 50km north of
Perth, WA.
This recommendation followed significant progress during
the quarter towards finalising the environmental approvals
process.
Boyatup Silica Sand
Project, 100km east of
Esperance, WA.
In late October 2024, VRX arranged a site visit to the
Arrowsmith North project for representatives from various
government agencies involved in the assessment process,
including the EPA Board, the EPA Services division of the
Department for Water and Environmental Regulation
(DWER), the Department of Biodiversity, Conservation and
Attraction (DBCA) and the Commonwealth Department of
Climate Change, Energy, the Environment and Water
(DCCEEW), which manages the Environment Protection
and Biodiversity Conservation Act 1999 (EPBC Act).
Geothermal Energy
Dandaragan Geothermal
Energy Permit, 145km
north of Perth, WA
The Company is actively
assessing other silica sand
and downstream
processing projects in
Australia.
The visit enabled these agencies with a first-hand observation and understanding of the
environment relevant to the project mining and processing proposal. The site visit was a prerequisite for final assessment of the project by the EPA.
In mid November 2024 the Company announced that the EPA had accepted the Response to
Submissions (RtS) for Arrowsmith North and published the RtS on the EPA website.
Acceptance and publication of the RtS was a significant milestone for the project as it
confirmed the EPA will finalise its assessment of Arrowsmith North. The stages of the
approvals process that follow publication are subject to statutory timeframes, giving greater
certainty of timing for determination of an approval outcome.
Prior to being published on the EPA website, the RtS was reviewed by the various government
agencies involved in the assessment process. It included minor revisions to the project to
reduce impacts to priority flora and also details VRX’s commitments to ensure the best
rehabilitation techniques are undertaken and monitored and outcomes reported.
The revisions included an amendment to the final Mine Development Envelope (MDE) to avoid
significant flora species on the perimeter of the MDE. This change reduces the impact on
recorded flora species and is effected by a request to amend the Project during assessment
under section 43A of the Environmental Protection Act 1986 (EP Act). The amendment has
been assessed and approved by the EPA. This consultation and acceptance by the EPA of
the RtS confirmed to VRX that these issues are not prohibitive to the EPA completing its
assessment of the project.
As the project has evolved since the original referral to DCCEEW under the EPBC Act, the
Company sought a variation to the project under section 156A of the EPBC Act. DCCEEW
has confirmed that this amendment has been accepted. The amendment does not have a
significant impact on the project’s future production from an extensive +200Mt Reserve.
VRX was invited to attend and present the project to the EPA Board at a meeting in November
2024 subsequent to publication of the RtS, at which the EPA Board considered the EPA’s draft
assessment report for the project (Report) and EPA Board members were able to discuss the
project and remaining key issues raised by the RtS directly with representatives of the
Company, including proposed conditions attaching to an approval for the project
(Conditions), ahead of the EPA finalising its assessment report and making a
recommendation to the Minister for Environment within the 12 week statutory timeline.
Subsequent to the end of the quarter, in early January 2025 the Company announced that the
EPA had published its Report and the Conditions on the EPA website, in which the EPA
recommends that the Arrowsmith North development proposal may be implemented subject
to the Conditions, which had been accepted by VRX following consultation with the EPA during
December 2024. The Conditions are a summary of standard requirements for mining
operations and commitments made by the Company in the RtS, incluidng rehabilitation and
mine closure procedures.
Publication of the Report triggers a three-week review period. Following this period and
resolution of any appeals by an independent appeals convenor, the Minister for Environment
will consider approval of the Arrowsmith North development proposal under Part IV of the EP
Act.
The environmental approvals process for Arrowsmith North is expected to finalise by the end
of the March 2025 quarter, including approvals required from DCCEEW. Other permitting
approvals processes (see below) have run in parallel to the environmental approvals process
and decisions in that regard are expected to follow promptly after the environmental approval
decision is handed down by the Minister.
2
Arrowsmith North Offtake
Subsequent to the end of the quarter, in mid January 2025 the Company announced that it
had entered into additional non-binding offtake term sheets for the supply of silica sand
foundry products from Arrowsmith North into the foundry industries in the Republic of Korea
(South Korea), Japan and Taiwan.
The offtake parties are all significant suppliers in their respective countries. Namgwang
Casting Materials Ind Co., Ltd and Woori Corporation, are leading suppliers of sand to the
foundry industry in South Korea. Yamakawa Sangyo Co., Ltd is a leading supplier to the
foundry industry in Japan. FarnHwa Enterprise Co., Ltd is a leading supplier of foundry and
glassmaking sand in Taiwan.
The term sheets set out detailed terms and conditions for the supply of an aggregate 440,000
tonnes per annum of AFS20, 35 and 55 certified foundry sand for a period of four years, with
indicative pricing within the range of the Company’s financial modelling for Arrowsmith North
as provided in the updated bankable feasibility study for the project announced to ASX in
March 2024.
Key assumptions for the BFS include a target price range of US$38-43 per dry metric tonne,
dependent on product type, product quality, contract terms and quantity, and a targeted
production schedule of 2.2 million tonnes per annum over the full mine life with a conservative
ramp up from a minimum 800,000 tonnes to 1.1 million tonnes per annum in years 1 and 2.
The Company now has offtake interest under term sheet for an aggregate of 640,000 tonnes,
which includes the 200,000 tonnes sought by Dong A and Dong Nam in South Korea.
Arrowsmith North Project Financing
During the quarter the Company continued to explore project financing alternatives, including
debt and offtake finance for Arrowsmith North.
In the light of progress towards conclusion of the environmental approvals process for
Arrowsmith North, interest from potential debt financiers has increased markedly and the
Company has commissioned an independent technical review for Arrowsmith North.
This work has continued subsequent to the end of the quarter.
Arrowsmith North Water Supply
The proposed Arrowsmith North processing plant requires a reliable source of water to enable
the appropriate treatment of raw material into the required final products.
The Company lodged an application for a water allocation and permit to construct a bore in
September 2021 which was drilled and completed in January 2022. Following an extensive
pumping and testing program the Company then lodged a request for a Groundwater
Abstraction Licence in October 2022 (Licence). The proposal was advertised in August 2024
and no comments were received during the comment period.
During the quarter there has been no request for additional information and, based on the
Company’s engagement with DWER, it is anticipated that the approval for the Licence request
and final water allocation will be finalised in parallel with Ministerial consent for Arrowsmith
North.
3
Arrowsmith North Mining Proposal
The Mining Proposal approval refers to the authorisation given by the Department of Energy,
Mines, Industry Regulation and Safety (DEMIRS) for a mining project to proceed. The approval
is based on the submission of a comprehensive document outlining the proposed mining
activities, environmental management plans, and rehabilitation strategies. This approval is
essential for ensuring that mining operations comply with legal, environmental and safety
standards.
The Company lodged a Mining Proposal with DEMIRS in September 2023 which was followed
by a request for further information in May 2024. A response was provided by the Company
in September 2024 following detailed analysis of pre and post mining soil profiles.
Following the publication of the EPA’s assessment report for Arrowsmith North and the
Conditions subsequent to the end of the quarter, the Mining Proposal has been reviewed to
comply with the Conditions and a revised Mining Proposal will be lodged with DEMIRS.
It is anticipated that the assessment of the Mining Proposal and approval will also be finalised
in parallel with Ministerial consent for Arrowsmith North.
Arrowsmith North Part V Works Approval
A Works Approval from DWER grants authority under Part V of the EP Act to construct, install,
or modify a facility that could potentially impact the environment. A Works Approval is required
when a project meets the description and design capacity of a ‘prescribed premises category’
defined in the Environmental Protection Regulations 1987. It is usually required for projects
that involve industries such as ore processing, waste management, manufacturing, or other
activities that generate significant emissions to air, water, or land and present a pollution risk.
A Works Approval application for Arrowsmith North was lodged with DWER on July 2023 for
a Category 5 Silica Sand Processing Plant. Subsequent to the end of the quarter, the
Company received a Draft Works Approval and Draft Decision Report which has invited the
Company to comment on the Approval Conditions and Decision Report and supply additional
information on certain minor matters.
Based on the assessment to date, the Company understands that it is DWER’s intention to
grant the application. The granting of the Works Approval is contingent on the determination
of the proposal under Part IV of the EP Act, and the publication of the Ministerial consent for
Arrowsmith North.
Silica Flour Program and Investment Attraction Fund Grant
The Company has completed a business case for production of silica flour and has further
investigated the markets for the finer by-product produced during the silica flour beneficiating
process.
Silica flour for LCD glass is only one of the potential commercial outcomes from the grinding
program.
During the quarter the Company continued investigating opportunities from further processing
of the silica flour which may lead to other in-demand higher grade silica products.
These research and development activities, which start with the production of silica flour, will
result in other downstream processing opportunities that will maximise the value of VRX’s
world-class high-quality Muchea Silica Sand Project.
4
The Western Australian State Government is contributing to the testwork program and
potentially the pilot plant required through the Investment Attraction Fund grant announced in
July 2023.
Capital Raising
In December 2024 the Company raised $5 million (before costs) via a placement of fully paid
ordinary shares to professional and sophisticated investors at an issue price of 4.2 cents each.
The placement comprised the issue of approximately 115.5 million new shares equating to
approximately $4.85 million within the Company’s placement capacity under Listing Rule 7.1
(52,650,625 shares) and 7.1A (62,825,567 shares) and the issue of approximately 3.6 million
new shares equating to approximately $150,000 to VRX directors, subject to shareholder
approval under Listing Rule 10.11 to be sought at a general meeting expected to be held later
this quarter.
The placement attracted strong interest and was well supported by existing shareholders and
new institutional investors, including a substantial commitment by major shareholder Sparta
Invest AG of $2 million.
ASX Listing Rule 5.3 Disclosures
Details of mining exploration activities:
Payments for exploration & evaluation under operating activities of $269,000 related mainly to
tenement rents and rates.
Payments for exploration & evaluation under investing activities of $238,000 consists mainly
of environmental surveys and approval costs.
There were no substantive mining production and development activities during the quarter.
Details of tenement activities:
During the quarter, Exploration Licence E70/3560 Boyatup was granted retention status.
In addition, Mining Lease M70/1418 (Arrowsmith Brand) was converted into Retention Licence
R70/64 and Mining Lease M70/1392 (Arrowsmith Central) was converted into Retention
Licence R70/65.
Details of related party payments:
The aggregate amount of payments to related parties and their associates of $67,000
represents directors’ fees and salaries paid during the quarter.
This quarterly activities report has been approved for release by the Managing Director.
Further information:
Bruce Maluish
Managing Director
brucem@vrxsilica.com.au
0418 940 417
Peter Klinger
Purple
pklinger@purple.au
0411 251 540
5
Combined 1.4Bn tonne Mineral Resource
Table 1 Mineral Resource Statement (as at 31 December 2024)
Project
Mt
SiO₂
%
Fe₂O₃
%
TiO₂
%
LOI
%
29
179
208
10
237
266
513
523
523
28.2
48.3
76.5
60
60
1,381
99.6
0.1
0.03
99.6
0.1
0.02
99.6
0.1
0.02
95.9
1.9
0.7
97.7
1.0
0.4
98.4
0.7
0.3
98.0
0.9
0.3
97.3
1.4
0.4
97.3
1.4
0.4
96.6
1.7
0.4
96.9
1.5
0.4
96.8
1.5
0.4
97.8
0.8
0.2
97.8
0.8
0.2
Million Tonnes
0.1
0.1
0.1
0.3
0.2
0.2
0.2
0.2
0.2
0.2
0.2
0.2
0.1
0.1
0.2
0.2
0.2
0.7
0.5
0.4
0.4
0.6
0.6
0.7
0.7
0.7
0.9
0.9
Classification
Indicated
Muchea
Inferred
Total
Measured
Indicated
Arrowsmith
North
Inferred
Total
Inferred
Arrowsmith
Brand
Total
Indicated
Arrowsmith
Inferred
Central
Total
Inferred
Boyatup
Total
Total Mineral Resource
Al₂O₃
%
Table 2 Ore Reserve Statement (as at 31 December 2024)
Project
Classification
Product
Mt
Muchea
Probable
F80
F80C
F150
AFS20
AFS35
Proved
AFS55
Local
Proved Ore Reserve
Arrowsmith
North
AFS20
AFS35
Probable
AFS55
Local
Probable Ore Reserve
Arrowsmith North Ore Reserve
CF400
C20
Arrowsmith
Probable
C40
Central
High TiO2
10.2
4.25
4.25
18.7
0.8
3.9
2.7
1.8
9.2
24.2
102.5
51.1
34.1
212
221
4.2
8.4
4.2
2.2
Arrowsmith Central Ore Reserve
Total Ore Reserve
18.9
259
Muchea Ore Reserve
SiO2
%
Al2O3
%
Fe2O3
%
TiO2
%
LOI
%
99.9
0.02
0.008
0.03
0.1
99.8
0.07
0.015
0.035
0.1
Million Tonnes
99.5
0.25
0.07
99.5
0.5
0.06
99.2
0.5
0.1
0.05
0.05
0.05
0.1
0.1
0.1
Million Tonnes
99.5
0.25
0.07
99.5
0.5
0.06
99.2
0.5
0.1
0.05
0.05
0.05
0.1
0.1
0.1
0.04
0.03
0.1
<1%
2%
Million Tonnes
Million Tonnes
99.6
0.25
Million Tonnes
Million Tonnes
6
Compliance Statement
The information in this document that relates to the estimation and reporting of the Mineral
Resource and Ore Reserves for the Company’s silica sand projects is extracted from releases
to ASX on 28 August 2019,11 November 2022 and 6 March 2024 (Arrowsmith North), 17
September 2019 (Arrowsmith Central), 9 May 2023 (Arrowsmith Brand), 18 October 2019
(Muchea) and Boyatup (18 August 2022). The Company confirms that it is not aware of any
new information or data that materially affects the information included in this document and
all material assumptions and technical parameters underpinning the estimates continue to
apply and have not materially changed.
The information in this announcement that relates to the previous exploration results have
been cross referenced to the original announcement. The Company is not aware of any new
information or data that materially affects the previous exploration results.
The Company confirms that the form and context in which the Competent Persons’ findings
are presented have not been materially modified.
7
Interests in Mining Tenements (Western Australia)
Arrowsmith Project – Silica Sand
Tenement
Status
E70/4987
E70/5027
E70/5817
M70/1389
M70/1392
R70/65
M70/1418
R70/64
L70/198
L70/199
L70/202
L70/203
L70/208
L70/229
L70/230
G70/264
G70/265
Granted
Granted
Granted
Granted
Converted
Granted
Converted
Granted
Granted
Granted
Granted
Granted
Granted
Application
Granted
Granted
Granted
Interest at
beginning of
quarter
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
Interests relinquished,
reduced or lapsed
Interests acquired
or increased
Interest at end
of quarter
100%
100%
-
100%
100%
-
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
Interests relinquished,
reduced or lapsed
Interests acquired
or increased
Interest at end
of quarter
-
-
100%
100%
100%
100%
100%
Interests relinquished,
reduced or lapsed
Interests acquired
or increased
Interest at end
of quarter
-
-
100%
Muchea Project – Silica Sand
Tenement
Status
E70/4886
E70/5651
M70/1390
M70/1414
L70/200
L70/204
L70/205
L70/206
Granted
Application
Granted
Application
Granted
Granted
Application
Granted
Interest at
beginning of
quarter
100%
100%
100%
100%
100%
Boyatup Project – Silica Sand
Tenement
Status
E69/3560
Retention
Interest at
beginning of
quarter
100%
8
About VRX Silica Limited
VRX Silica Limited (ASX: VRX) is the most advanced pureplay silica sand company listed on the
ASX, developing its 100% owned silica sand projects at Arrowsmith (North, Brand and Central),
Muchea and Boyatup in Western Australia.
Silica sand is the most used commodity on
the planet after air and water. It is the main
ingredient in all types of glassmaking,
including specialty solar panel and hightech glass, and foundry casting. It is a
finite resource that is running out, with the
Asia-Pacific region experiencing an evergrowing supply shortfall that is driving up
prices.
Arrowsmith is located 270km north of
Perth. Arrowsmith North boasts a minimum
25-year mine life capable of producing
more than 2Mt tonnes per year of highgrade (99.7% SiO2)* silica sand for export
to the foundry, container glass and flat
glass markets in Asia, with permitting well
advanced, and will lead production.
Muchea, located 50km north of Perth, is an
ultra-high-grade (99.9% SiO2)* silica sand
project capable of producing sand required
for ultra-clear glass for solar panels and
other high-tech glass applications.
Boyatup, located 100km east of Esperance,
is under development and capable of
producing sand for the glass market.
*Information relating to grades are extracted from releases to ASX on 28 August 2019, 11 November 2022 and 6
March 2024 (Arrowsmith North) and 18 October 2019 (Muchea). The company is not aware of any new information
or data that materially affects this information.
9
Rule 5.5
Appendix 5B
Mining exploration entity or oil and gas exploration entity
quarterly cash flow report
Name of entity
VRX SILICA LTD
Quarter ended (“current quarter”)
ABN
59 142 014 873
Consolidated statement of cash flows
1.
Cash flows from operating activities
1.1
Receipts from customers
1.2
Payments for
31 December 2024
Year to date
(6 months)
$A’000
Current quarter
$A’000
-
-
(269)
(505)
(b) development
-
-
(c) production
-
-
(d) staff costs
(207)
(457)
(e) administration and corporate costs
(274)
(578)
(a) exploration & evaluation
1.3
Dividends received (see note 3)
-
-
1.4
Interest received
5
13
1.5
Interest and other costs of finance paid (on
lease liability)
(5)
(10)
1.6
Income taxes paid
-
-
1.7
Government grants and tax incentives
-
144
1.8
Other (provide details if material)
-
-
1.9
Net cash from / (used in) operating
activities
(750)
(1,393)
2.
Cash flows from investing activities
2.1
Payments to acquire or for:
(a) entities
-
-
(b) tenements
-
-
(c) property, plant and equipment
-
(20)
(238)
(49)
(e) investments
-
-
(f)
-
-
(d) exploration & evaluation
other non-current assets
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
Page 1
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
Consolidated statement of cash flows
2.2
Year to date
(6 months)
$A’000
Current quarter
$A’000
Proceeds from the disposal of:
(a) entities
-
-
(b) tenements
-
-
(c) property, plant and equipment
-
-
(d) investments
-
-
(e) other non-current assets
-
-
2.3
Cash flows from loans to other entities
-
-
2.4
Dividends received (see note 3)
-
-
2.5
Other (bonds deposit)
-
-
2.6
Net cash from / (used in) investing
activities
(238)
(69)
3.
Cash flows from financing activities
3.1
Proceeds from issues of equity securities
(excluding convertible debt securities)
4,850
4,850
3.2
Proceeds from issue of convertible debt
securities
-
-
3.3
Proceeds from exercise of options
-
-
3.4
Transaction costs related to issues of equity
securities or convertible debt securities
(298)
(298)
3.5
Proceeds from borrowings
-
-
3.6
Repayment of borrowings
-
-
3.7
Transaction costs related to loans and
borrowings
-
-
3.8
Dividends paid
-
-
3.9
Other (repayment of lease liability)
(22)
(43)
3.10
Net cash from / (used in) financing
activities
4,530
4,509
4.
Net increase / (decrease) in cash and
cash equivalents for the period
4.1
Cash and cash equivalents at beginning of
period
1,818
2,313
4.2
Net cash from / (used in) operating
activities (item 1.9 above)
(750)
(1,393)
4.3
Net cash from / (used in) investing activities
(item 2.6 above)
(238)
(69)
4.4
Net cash from / (used in) financing activities
(item 3.10 above)
4,530
4,509
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
Page 2
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
Consolidated statement of cash flows
4.5
Effect of movement in exchange rates on
cash held
4.6
Cash and cash equivalents at end of
period
5.
Reconciliation of cash and cash
equivalents
Year to date
(6 months)
$A’000
Current quarter
$A’000
-
-
5,360
5,360
Current quarter
$A’000
Previous quarter
$A’000
at the end of the quarter (as shown in the
consolidated statement of cash flows) to the
related items in the accounts
5.1
Bank balances
2,360
1,818
5.2
Call deposits
3,000
-
5.3
Bank overdrafts
-
-
5.4
Other (provide details)
-
-
5.5
Cash and cash equivalents at end of
quarter (should equal item 4.6 above)
5,360
1,818
6.
Payments to related parties of the entity and their
associates
6.1
Aggregate amount of payments to related parties and their
associates included in item 1
67
6.2
Aggregate amount of payments to related parties and their
associates included in item 2
-
Current quarter
$A'000
Note: if any amounts are shown in items 6.1 or 6.2, your quarterly activity report must include a description of, and an
explanation for, such payments.
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
Page 3
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
7.
Financing facilities
Note: the term “facility’ includes all forms of financing
arrangements available to the entity.
Add notes as necessary for an understanding of the
sources of finance available to the entity.
Total facility
amount at quarter
end
$A’000
Amount drawn at
quarter end
$A’000
7.1
Loan facilities
-
-
7.2
Credit standby arrangements
-
-
7.3
Other (please specify)
-
-
7.4
Total financing facilities
-
-
7.5
Unused financing facilities available at quarter end
7.6
Include in the box below a description of each facility above, including the lender, interest
rate, maturity date and whether it is secured or unsecured. If any additional financing
facilities have been entered into or are proposed to be entered into after quarter end,
include a note providing details of those facilities as well.
8.
Estimated cash available for future operating activities
8.1
Net cash from / (used in) operating activities (item 1.9)
(750)
8.2
(Payments for exploration & evaluation classified as investing
activities) (item 2.1(d))
(238)
8.3
Total relevant outgoings (item 8.1 + item 8.2)
(988)
8.4
Cash and cash equivalents at quarter end (item 4.6)
5,360
8.5
Unused finance facilities available at quarter end (item 7.5)
8.6
Total available funding (item 8.4 + item 8.5)
8.7
Estimated quarters of funding available (item 8.6 divided by
item 8.3)
-
$A’000
5,360
5.43
Note: if the entity has reported positive relevant outgoings (ie a net cash inflow) in item 8.3, answer item 8.7 as “N/A”.
Otherwise, a figure for the estimated quarters of funding available must be included in item 8.7.
8.8
If item 8.7 is less than 2 quarters, please provide answers to the following questions:
8.8.1
Does the entity expect that it will continue to have the current level of net operating
cash flows for the time being and, if not, why not?
Answer: Not applicable
8.8.2
Has the entity taken any steps, or does it propose to take any steps, to raise further
cash to fund its operations and, if so, what are those steps and how likely does it
believe that they will be successful?
Answer: Not applicable
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
Page 4
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
8.8.3
Does the entity expect to be able to continue its operations and to meet its business
objectives and, if so, on what basis?
Answer: Not applicable
Note: where item 8.7 is less than 2 quarters, all of questions 8.8.1, 8.8.2 and 8.8.3 above must be answered.
Compliance statement
1
This statement has been prepared in accordance with accounting standards and policies which
comply with Listing Rule 19.11A.
2
This statement gives a true and fair view of the matters disclosed.
Date:
.....30 January 2025...........
Authorised by: .....The Board....................
(Name of body or officer authorising release – see note 4)
Notes
1.
This quarterly cash flow report and the accompanying activity report provide a basis for informing the market about the
entity’s activities for the past quarter, how they have been financed and the effect this has had on its cash position. An
entity that wishes to disclose additional information over and above the minimum required under the Listing Rules is
encouraged to do so.
2.
If this quarterly cash flow report has been prepared in accordance with Australian Accounting Standards, the definitions
in, and provisions of, AASB 6: Exploration for and Evaluation of Mineral Resources and AASB 107: Statement of Cash
Flows apply to this report. If this quarterly cash flow report has been prepared in accordance with other accounting
standards agreed by ASX pursuant to Listing Rule 19.11A, the corresponding equivalent standards apply to this report.
3.
Dividends received may be classified either as cash flows from operating activities or cash flows from investing activities,
depending on the accounting policy of the entity.
4.
If this report has been authorised for release to the market by your board of directors, you can insert here: “By the board”.
If it has been authorised for release to the market by a committee of your board of directors, you can insert here: “By the
[name of board committee – eg Audit and Risk Committee]”. If it has been authorised for release to the market by a
disclosure committee, you can insert here: “By the Disclosure Committee”.
5.
If this report has been authorised for release to the market by your board of directors and you wish to hold yourself out as
complying with recommendation 4.2 of the ASX Corporate Governance Council’s Corporate Governance Principles and
Recommendations, the board should have received a declaration from its CEO and CFO that, in their opinion, the financial
records of the entity have been properly maintained, that this report complies with the appropriate accounting standards
and gives a true and fair view of the cash flows of the entity, and that their opinion has been formed on the basis of a
sound system of risk management and internal control which is operating effectively.
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
Page 5