EPA approves ESD and sets timetable for Arrowsmith North
Released
Released
Announcement PDF
17 March 2022
ASX ANNOUNCEMENT
EPA approves Environmental Scoping Document,
sets timetable for Arrowsmith North
Highlights:
•
EPA approves Environmental Scoping Document for
Arrowsmith North
ASX: VRX
Capital Structure
•
Significant milestone and provides clarity on pathway
to final environmental approval
Shares on Issue:
558.4 million
Unlisted Options:
35.3 million
•
Cements Arrowsmith North’s position as WA’s most
advanced silica sand development project
Corporate Directory
VRX Silica Limited (VRX or Company) is pleased to announce
that the Environmental Protection Authority of Western Australia
(EPA) has approved the Company’s Environmental Scoping
Document (ESD) for proposed mining activities (Proposal) at
its 100% owned Arrowsmith North Silica Sand Project
(Arrowsmith North), approximately 270km north of Perth in
Western Australia.
The approval required no amendments to the submitted ESD
document which is testament to the process that VRX has
undertaken in consultation with the EPA.
Paul Boyatzis
Non-Executive Chairman
Bruce Maluish
Managing Director
Peter Pawlowitsch
Non-Executive Director
David Welch
Non-Executive Director
Ian Hobson
Company Secretary
EPA approval of the ESD is a significant milestone in the
environmental approvals process for Arrowsmith North and
provides clarity for the Company on the pathway to
development.
Silica Sand Projects
The ESD is a precursor to the Environmental Review Document
(ERD), which is required under the EPA’s public environmental
review process and will be released for public review. The ESD
was prepared according to the procedures in the EPA’s
Environmental Impact Assessment (EIA; Part IV Divisions 1 And
2) Procedures Manual (EPA, 2021b)
Muchea Silica Sand
Project, 50km north of
Perth, WA.
Importantly, VRX now has an indicative timetable for full
assessment acceptance by the EPA, with a final report for
Ministerial environmental approval scheduled for December
2022.
The indicative timetable, which is set out on the following page,
enables VRX to plan and schedule key development activities
for Arrowsmith North including financing, capital investment (in
particular for long-lead items) and construction.
Arrowsmith Silica Sand
Projects, 270km north of
Perth, WA.
Boyatup Silica Sand
Project, 100km east of
Esperance, WA.
The Company is actively
assessing other silica
sand projects in
Australia.
VRX has already completed process engineering, site geotechnical works and bore
installations while detailed engineering for fabrication is underway.
VRX’s Managing Director Bruce Maluish said: “EPA approval of our Environmental
Scoping Document is the culmination of many months of hard work by both VRX and the EPA
and we look forward to continued collaboration as we progress the development of the
Arrowsmith North Silica Sand Project.
“The ESD provides the scope of studies required for the next stage of the approvals process,
the Environmental Review Document, the draft of which is well advanced, and gives us clarity
on the pathway forward to full approval and development of Arrowsmith North.
“Arrowsmith North is the first of our three high-quality, world-scale projects and the most
advanced pure silica sand development opportunity in Western Australia. I am confident the
lessons from this approvals process will assist VRX as we progress approvals and
development of the Arrowsmith Central and Muchea silica sand projects.
“Based on the indicative timetable now available to the Company, VRX expects to begin
Arrowsmith North’s six-month construction period in January 2023.”
“I thank our shareholders for their ongoing support and patience as we progress our three
100%-owned, world-class, high-grade silica sand projects toward production and the delivery
of sustained value.”
Key assessment milestones
Indicative date
Proponent submits first draft ERD
15 April 2022
EPA provides comment on first draft ERD
(6 weeks from receipt of ERD)
EPA accepts ERD (assumes no further revisions required)
27 May 2022
EPA authorises release of Environmental Review Document for public review
(2 weeks from EPA approval of ERD)
10 June 2022
Proponent releases Environmental Review Document for public review for 4
weeks
Close of public review period
10 June 2022
27 May 2022
8 July 2022
EPA provides Summary of Submissions
(3 weeks from close of public review period)
29 July 2022
Proponent provides Response to Submissions
19 August 2022
EPA reviews the Response to Submissions
(4 weeks from receipt of Response to Submissions)
16 September 2022
EPA accepts and publishes proponent’s response to submissions
16 September 2022
EPA prepares draft assessment report and completes assessment
(6 weeks from acceptance of proponent’s response to submissions)
28 October 2022
EPA finalises Assessment report (including two-week consultation on draft
conditions) and gives report to Minister
(6 weeks from completion of assessment)
9 December 2022
In parallel to the approvals process, VRX has been busy advancing key aspects of Arrowsmith
North’s development including engineering design and financing discussions. Based on the
indicative timetable provided by the EPA’s sign-off of the ESD, the Company expects to be on
the ground at Arrowsmith North and commence the six-month construction period in January
2023, subject to Ministerial approval.
Update on DMIRS approval process
VRX has commenced the Department of Mines, Industry, Regulation and Safety (DMIRS)
approvals process for Arrowsmith North with a presentation of the Mining Proposal and
Closure Plan to the relevant department assessment officers.
A final document will be lodged with DMIRS by the end of March 2022.
DMIRS has confirmed that its approvals process will run in parallel with the EPA approvals
process and final approval will be subject to Ministerial approval.
Commonwealth Government approvals process
The Arrowsmith North Proposal had been referred to the Commonwealth Department of
Agriculture, Water and the Environment (DAWE) and determined to be a controlled action
under the Environment Protection and Biodiversity Conservation Act 1999 (EPBC Act).
DAWE had also confirmed that the Proposal would be assessed under a Bilateral Agreement
between the Commonwealth and the State of Western Australia under section 45 of the EPBC
Act or an accredited process under section 87 of the Act.
The ESD completed by VRX, and approved by the EPA, includes work required to be carried
out and reported on in the ERD in relation to ‘Matters of National Environmental Significance’.
The ERD will also address the matters in Schedule 4 of the regulations to the EPBC Act.
Update on Arrowsmith Central Approvals
VRX commenced the approvals process for the Arrowsmith Central Silica Sand Project with a
referral submission to DAWE under the EPBC Act in October 2021. DAWE determined that
under section 75 of the EPBC Act the proposed action is a controlled action and, as such, it
requires assessment and a decision about whether approval for it should be given under the
EPBC Act.
Furthermore, the Company lodged a Section 38 Referral and supporting documentation to the
State Department of Water and Environmental Regulation (DWER) in September 2021, which
has a description of the Arrowsmith Central proposal, affected areas, key environmental
factors, impact assessments and identified approvals and regulations.
The EPA requested additional information which was provided with an updated Referral in
February 2022. The Company has received no further notifications at this time.
This announcement has been authorised for release to the ASX by VRX Managing Director
Bruce Maluish.
Further information:
Bruce Maluish
Managing Director
brucem@vrxsilica.com.au
0418 940 417
Peter Klinger
Cannings Purple
pklinger@canningspurple.com.au
0411 251 540
About VRX Silica
VRX Silica Ltd (ASX: VRX) is developing world-class, high-grade silica sand projects in Western Australia.
The Arrowsmith North and Arrowsmith Central Silica Sand Projects, 270km north of Perth, comprise five granted
exploration licences and two granted mining leases. Bankable feasibility studies for both projects have demonstrated
exceptional financial metrics.
The Muchea Silica Sand Project, 50km north of Perth, comprises two granted and one under-application exploration
licences as well as one granted mining lease. Muchea is a world-class project with high-purity silica sand in situ. A
bankable feasibility study has demonstrated outstanding financial metrics.
The Boyatup Silica Sand Project, 100km east of Esperance, comprises two adjacent granted exploration licences.
Initial indications are that this project can complement the Arrowsmith North and Arrowsmith Central, and Muchea
projects.
Proven Management
VRX Silica’s Board and Leadership Team have extensive experience in mineral exploration and mine developmentto-production and in the management of publicly listed mining and exploration companies.
Project Locations
Share your feedback
Discover