Quarterly Activities Report
Released
Released
Announcement PDF
The following is a summary of the activities of VRX Silica Ltd (VRX Silica or Company)
(ASX: VRX) during the quarter ending 31 December 2018.
VRX Silica has two silica sand projects at Arrowsmith and Muchea, 270km and 50km north
of Perth, respectively, which contain a combined total Mineral Resource of silica sand of 412
million tonnes. See locations below:
Exploration
Figures 1 and 2: Muchea (Left) and Arrowsmith (Right) Silica Sand Projects
Bulk Sampling Testwork
VRX Silica has completed bulk sampling at both projects – air core drilling and hand auger at
Muchea, and hand auger at Arrowsmith – as announced to ASX on 30 July 2018 “Muchea
Acquisition and Capital Raising” and 30 August 2018 “Arrowsmith Silica Sand Project”.
The drill samples were used to generate four bulk composites for metallurgical testwork for
Muchea (air core drilling only sampling), Arrowsmith North, Arrowsmith Central and
Arrowsmith South (hand auger sampling).
The composite was sent to the CDE Global (CDE) facility in Cookstown, Ireland, a specialist
sand metallurgical testing laboratory with the intention of gaining a better understanding of
the sand characteristics when subjected to standard processing techniques.
The CDE testwork highlighted the potential for further improvements by utilising specialist
processing equipment in the attritioning and magnetic separation steps. The attrition test
uses a high-speed shaft with paddles at a high slurry density of 75% solids to liberate fine
particles.
The magnetic separation step involved pumping a slurry through a magnetised matrix “Hi
Intensity Magnetic Filter”, which separates the feed into three distinct fractions: magnetics,
middlings and non-magnetics, dependant on the magnetic susceptibility of the individual
sand grains.
Table 2 below shows the results of the magnetic separation tests for the 4 project areas. The
results demonstrate that a HI Filter can very effectively separate out the pure quartz grains
from those which contain deleterious elements.
Table 1: Magnetic Separation Testwork Results
PROCESS STAGE
Muchea
Magnetic Separation
Arrowsmith North
Magnetic Separation
Arrowsmith Central
Magnetic Separation
Arrowsmith South
Magnetic Separation
SAMPLE
DESCRIPTION
Magnetics
Middlings
Non magnetic
Magnetics
Mids
Non magnetic
Magnetics
Middlings
Non magnetic
Magnetics
Mids
Non magnetic
Mass Al 2O3
%
ppm
0.41%
1,245
7.31%
335
92.27%
262
0.63%
5,069
9.33%
1,762
90.04% 1,797
0.71% 16,006
11.24% 2,863
88.06% 2,566
0.70% 15,696
8.26%
6,104
91.04% 7,311
CaO
ppm
175
50
49
403
48
46
424
71
68
1,873
135
149
Cr2O3 Fe 2O3
ppm
ppm
14 2,521
2
90
2
68
75 15,456
3
453
3
414
419 44,243
5
749
3
341
254 43,891
5
624
4
470
K2O
ppm
196
51
38
904
238
276
1,379
827
785
4,046
2,972
3,847
MgO
ppm
128
14
12
518
22
20
471
31
22
1,553
45
32
MnO
ppm
57
1
1
433
2
2
834
7
2
1,301
5
2
Na2O
TiO2
ppm
ppm
117 3,756
30
207
21
179
126 22,668
36
255
33
198
141 36,954
74
676
69
267
405 54,561
225
476
289
193
LOI1000C
SiO2 + LOI
%
0.21
99.18
0.05
99.92
0.10
99.94
0.39
95.43
0.10
99.72
0.09
99.72
1.08
89.91
0.18
99.47
0.13
99.59
0.74
87.64
0.22
98.94
0.15
98.77
The ASX announcement on 20 September contained detailed images of the CDE flowsheet,
the composite drill hole locations for both Arrowsmith and Muchea, tables showing grades
and bulk testwork results, comparison charts of raw material vs attritioned and washed
samples as well as the CDE lab scale attrition cell. The detail provided was extensive and
complete and further detailed information is within the 20 September 2018 ASX
announcement.
The results of the CDE testwork have confirmed that the Muchea, Arrowsmith North and
Arrowsmith Central projects can produce a sought-after product for glassmaking. This
enabled a JORC compliant Mineral Resource to be estimated for these projects and CSA
were engaged to conduct an independent Resource Estimate on the Arrowsmith North
Mineral and Arrowsmith Central deposits which was completed during the quarter.
Having established the Arrowsmith Silica Sand Project Resource Estimate early in the
quarter, VRX Silica continued working towards the Mineral Resource Estimate at the
Company’s Muchea Project which was also completed during the December quarter.
A further iteration of testwork was commenced by CDE using a refined flow sheet to
incorporate additional attritioning to further improve the quality of the potential final products
for Muchea, Arrowsmith North and Arrowsmith Central. The results of this work will be
followed by a process circuit design and engineering which will allow for capital cost
estimates to be generated.
Maiden Mineral Resource Estimate for Arrowsmith North
VRX Silica engaged CSA Global (CSA) to prepare a maiden Mineral Resource estimate
(MRE) for the Arrowsmith North target area reportable under the guidelines of the JORC
Code and on 2 October 2018 the Company announced the Arrowsmith North MRE comprises
193.6 Mt @ 98% SiO2 reported in accordance with the JORC Code 20121 Edition. The MRE
exceeds the previous Exploration Target of 100 to 140 million tonnes at 95% to 98% SiO2.
The MRE is based on the results obtained from 62 hand auger drill holes to a depth of 4-5
metres for 235.6 m and defines two silica sand types, white and yellow sand, geologically
logged and differentiated based on colour and through chemical analysis results. Based on
metallurgical testwork completed to-date, both sand types are readily amenable to upgrading
by conventional washing and screening methods to produce a high-purity silica sand product
with high mass recoveries. The high-purity silica sand product specifications are expected to
be suitable for industries such as glass making. The MRE results are shown in Table 2.
Table 2:
Classification
Inferred
Arrowsmith North Mineral Resource
Domain
Million Tonnes
SiO2%
Al2O3%
Fe2O3%
LOI%
TiO2%
Yellow Sand
149.4
97.7
1.1
0.4
0.5
0.2
White Sand
44.2
99.1
0.3
0.1
0.2
0.2
All Sand
193.6
98.0
0.9
0.3
0.4
0.2
*Note: Interpreted mineralisation is domained into different sand types based on drill logging data and publicly
available soil mapping information, above a basal surface wireframe defined based on the current drill sampling
depths. Depletion zones include the upper 0.5 m for rehabilitation purposes, and minor swamp zones in the east
and south of the modelled area. Differences may occur due to rounding.
The Mineral Resource is classified as Inferred according to the principles contained in the
JORC Code. Material that has been classified as Inferred was considered by the Competent
Person to be sufficiently informed by geological and sampling data to imply but not verify
geological and grade continuity between data points.
The project area is a substantial prominent dune system that has only been tested with
shallow auger. The Company has an approved Program of Works (PoW) to infill the
Arrowsmith North Inferred Mineral Resource and add to it substantially and with the intention
of upgrading the resource to an Indicated category. The Company has also completed an
Aboriginal Heritage clearance survey over the PoW area. This drilling will be done by an
Aircore drill rig which will not have the depth limitations of the hand auger technique and the
full depth of sand will be drill tested.
1
Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves. The JORC
Code, 2012 Edition. Prepared by: The Joint Ore Reserves Committee of The Australasian Institute of Mining and
Metallurgy, Australian Institute of Geoscientists and Minerals Council of Australia (JORC).
The drilling program will consist of 105 holes with an average depth of 11.3m (in
comparison, the average depth of hand auger holes was 3.8m) and is expected to
commence in the March quarter 2019. Upon completion of this work the Mineral Resource
estimate at the Company’s Arrowsmith Central prospect will be updated.
The initial exploration program also provided a bulk sample which was used for the second
iteration of metallurgical testwork and has verified that the sand can be beneficiated to glass
making quality (VRX announcement 20 September 2018). An additional third iteration of
testwork, which is underway, is expected to improve on the currently known quality.
The Company has had a number of enquiries from potential customers in Asia and now that
this Mineral Resource estimate has been established VRX Silica can accelerate the
Company’s marketing program for potential sales in Asia.
Maiden Mineral Resource Estimate for Arrowsmith Central
On 13 December 2018 VRX Silica Limited announced the results from the CSA independent
estimate of the Mineral Resource at its Arrowsmith Central prospect. The result is based on
an exploration program of 39 hand-held auger drill holes and is an acceptable standard for
use in a Mineral Resource estimate publicly reported in accordance with the JORC Code.
The Resource area is a small portion of the tenement area, adequate for initial mining studies
which can be increased substantially with future aircore drilling over an increased area.
Additional drilling is planned for early 2019 with the Company having recently completed an
extensive Aboriginal Heritage survey with representatives of the Southern Yamatji claimant
group for a more intensive and wider ranging drill program.
Table 3:
Arrowsmith Central Mineral Resource
Classification
Million Tonnes
SiO2%
Al2O3%
Fe2O3%
K2O%
LOI%
TiO2%
Inferred
28
97.7
1.2
0.3
0.3
0.5
0.2
*Note: Interpreted silica sand layer is domained above a basal surface wireframe defined based on the current
drill sampling depths. A depletion zone consisting of the upper 0.5 m is reserved for rehabilitation purposes, is not
estimated or reported. Differences may occur due to rounding.
The Arrowsmith Central Project is immediately adjacent to the Eneabba – Geraldton rail line,
which offers a unique low capex logistics solution to export bulk products out of Geraldton.
This resource adds to the two previously announced silica sand resources, Arrowsmith North,
“Arrowsmith North Maiden Mineral Resource” 2 October 2018, and Muchea, “Muchea Silica
Sand Project Maiden Resource” 20 November 2018.
Maiden Mineral Resource Estimate for Muchea
On 20 November 2018 VRX Silica announced the results from the independent estimate of
the Mineral Resource at its Muchea Silica Sand Project (Muchea Project), which is located
50km north of Perth.
The Mineral Resource estimate (MRE) for the Muchea Project comprises a combined total of
Indicated and Inferred Mineral Resources of 191 Mt @ 99.6% SiO2 reported in accordance
with the JORC Code 2012 Edition. The Indicated component of the MRE comprises 19 Mt @
99.7% SiO2, with the Inferred component being 172 Mt @ 99.6% SiO2.
The MRE was carried out by CSA and based on 44 hand auger drill holes for 260.7 m and
46 aircore holes for 522 m carried out by VRX in July 2018.
The MRE results are shown in Table 4.
Table 4: Muchea White Silica Sand Mineral Resource Estimate as at November 2018
Classification
Million Tonnes
SiO2%
Al2O3%
Fe2O3%
LOI%
TiO2%
Indicated
19
99.7
0.03
0.03
0.2
0.08
Inferred
172
99.6
0.04
0.02
0.2
0.08
Indicated + Inferred
191
99.6
0.04
0.02
0.2
0.08
*Note: Interpreted white silica sand mineralisation is domained above a basal surface wireframe defined based
on drill logging data. The upper (overburden) layer within 0.5 m of surface is depleted from the modelled silica
sand unit, being reserved for rehabilitation purposes. All classified silica sand blocks in the model are reported.
Differences may occur due to rounding.
The large Maiden MRE of high-grade silica sand vindicates the Company’s decision to
acquire the Muchea Project which the Company believes is a world class high-grade
deposit, which can be processed to supply almost any grade sand for glassmaking in Asia.
The area of the Inferred Mineral Resource estimate is predominately based on shallow hand
auger results and has the potential to be deeper with a significantly larger Mineral Resource.
The MRE defines the upper white silica sand layer, geologically logged and differentiated
based on colour and chemical analysis results.
The Company believes that the Indicated Mineral Resource area is adequate for detailed
mining studies, and closer spaced drilling will also extend the area and tonnage for a
potential Ore Reserve.
A composite of the samples gained during the due diligence work was sent to the CDE
facility in Cookstown, Ireland. The Bulk testwork returned the following results, Table 5
below, after de-sliming, attritioning, spirals and magnetic separation. The final product grade
and particle sizes as reported are considered to be of glass making quality.
Table 5:
SAMPLE
MATERIAL
MUCHEA
CDE Global Bulk Testwork results
SAMPLE
DESCRIPTION
Al2O3
Fe2O3
K2O
TiO2
LOI1000C
ppm
ppm
ppm
ppm
Raw Material
562
175
54
Final Product
262
68
38
%
SiO2
Calc.
SiO2 +
LOI
414
0.23
99.64
99.87
179
0.1
99.84
99.94
A further iteration of testwork has been commenced by CDE using a refined flow sheet to
incorporate additional attritioning to further improve the quality of the potential final products
to produce a high-quality feedstock for ultra-clear glass production.
Upon receipt of this work VRX Silica will move quickly into detailed process circuit design,
engineering and mining studies to support mining proposals and capital cost estimates as
well as for forwarding to relevant Government agencies to commence the approvals
process.
Maiden Mineral Resource Estimate Totals
Table 8: Total Silica Sand Mineral Resource, Arrowsmith North, Arrowsmith Central and Muchea
Indicated
Tonnes
Grade
(millions tonnes)
Prospect
Inferred
Tonnes
Total
Grade
Tonnes
Grade
(% SiO2) (millions tonnes) (% SiO2) (millions tonnes) (% SiO2)
Arrowsmith North
193.6
98.0%
193.6
98.0%
Arrowsmith Central
28
97.7%
28
97.7%
Muchea
19
99.7%
172
99.6%
191
99.6%
Total
19
99.7%
393.6
98.7%
412.6
98.7%
Arrowsmith North Mining Lease Application
On 24 December 2018 VRX Silica Limited announced the lodgement of its first silica sand
Mining Lease Application, MLA70/1389 at its Arrowsmith North prospect.
.
The MLA Resource at 73mt @ 97.7% SiO2 is only a small portion of the total Resource of
193.6 Mt @ 98% SiO2 but is expected to increase with deeper drilling than the hand-auger
sampling previously undertaken to estimate the Resource.
This Resource is contained within the previously announced silica sand Resource at the
Company’s Arrowsmith North prospect, “Arrowsmith North Maiden Mineral Resource” of 2
October 2018.
This is the first of three Mining Lease applications that the Company will lodge in the short
term and this Mining Licence application will enable the Company to apply for a Mining Permit
at Arrowsmith North early in the 2019 year.
The Company recently announced that it has received interest from potential offtake partners
for silica sand in quantities and grades that can be supplied from the Arrowsmith Silica Sand
Project, “Three LOIs for Silica Sand Offtake” of 11 December 2018.
The Arrowsmith North Mining Lease Application MLA70/1389 has an area of 1,728Ha, see
Table 6 below, and covers part of the Exploration Licences E70/5027 and E70/5109, Figure
1, which were granted on 14/06/2018 and 14/08/2018 respectively.
Table 6: Arrowsmith North tenement details
Tenement
Holders
Application date
Area (km2)
MLA70/1389
Ventnor Mining Pty Ltd
21/12/2018
17.3
CSA has reported the Mineral Resource which is located within the MLA boundary and is
summarised in Table 7, below.
Table 7: Arrowsmith North Silica Sand Mineral Resource estimate within MLA
Classification
Million Tonnes
SiO2%
Al2O3%
Fe2O3%
LOI%
TiO2%
Inferred
73.2
97.7
1.1
0.4
0.5
0.2
* Note: Mineral Resources are reported only from within the VRX nominated MLA and
form a subset of the total Arrowsmith North Mineral Resources as reported to the ASX
on 2 October 2018. Differences may occur due to rounding.
A Programme of Works for aircore drilling has been approved by DMIRS and the Aboriginal
Heritage Survey was completed during the quarter. This drilling, which will improve the
JORC classification, deepen and extend the current Mineral Resource, is expected to be
completed in the March Quarter 2019.
Silica Sand Geology - Arrowsmith North
Most economically significant silica sand deposits in Western Australia are found in the
coastal regions of the Perth Basin, and the targeted silica sand deposits are the aeolian
sand dunes that overlie the Pleistocene limestones and paleo-coastline, which also host the
regional heavy mineral deposits. Within the project area, data obtained from the Department
of Agriculture soil mapping shows there are pale and yellow deep sands predominating with
lesser swampy areas and occasional ironstone ridges. See Figure 3 and 4 below:
Figure 3: Cross section A – B at 6738150 mN (See Figure 4), Looking north; 10 times Vertical exaggeration
Figure 4: Simplified geology of the Arrowsmith North Area. Section line A – B shown.
Tenements as in Figure 2
Source: Outlines based on DOAG soil mapping data, refined based on drill data.
Silica Sand Geology - Muchea
Whereas most economically significant silica sand deposits in Western Australia are found in
the coastal regions of the Perth Basin, the targeted silica sand deposits at Muchea are
hosted by the Bassendean Sand, which extends over large areas of the Swan coastal plains
of the Perth Basin.
The term Bassendean Sand was introduced by Playford and Low (1972) for the widespread
unit of quartz sand extending over large areas of the coastal plain, from about 23 km north of
Jurien, to about 15 km southwest of Busselton (Figure 5). The Bassendean sand is thought
to have a maximum thickness of about 45 m, and the unit is found as a strip parallel to the
coast, having a width of about 10–20 km, and with its western edge about 5–10 km inland.
Quartz grains of the Bassendean Sand are interpreted as being derived from granitic rocks
in the Darling Range and have accumulated as shoreline and dune sands during two or
more periods of relatively stable sea level, ranging from about 8 to 25 m above present sea
level (Abeysinghe, 2003).
According to Abeysinghe (2003), the Bassendean Sand is typically clean, well rounded and
well sorted; however, its physical, chemical, and mineralogical characteristics can vary
considerably resulting in variation in the quality of the sand regionally as well as locally. The
sand is generally white near surface (Figure 6) but at depth it is usually high in iron and
yellow to brown in colour.
Figure 5:
Regional distribution of Bassendean Sand on the Swan Coastal Plain
The Bassendean Sand generally has little or no overburden and it is noted that a
discontinuous layer (generally less than a metre thick) of relatively hard ferruginous material,
known as ‘coffee rock’, at a depth ranging from less than a metre to about 15m below the
surface. Abeysinghe (2003) interpreted the coffee rock as having formed due to precipitation
of Fe oxides and hydroxides from circulating iron-rich groundwater. Below this layer, the
white sand can be quite thick, extending to a maximum of about 15m.
Soil mapping reported by Purdie et al. (2004, page 57; refer to Figure 3) described the
Bassendean Zone as comprising “fixed dunes inland from coastal dune zone”. The Pinjarra
Zone to the east was described as “alluvial deposits…..between the Bassendean Dunes
Zone and the Darling Scarp”. By comparison with the map presented by Abeysinghe (2003,
page 43. Map from Low, et al. 1978 and 1980) the Bassendean Zone is underlain by the
Bassendean Sand, while the Pinjarra Zone at Muchea is underlain by clays of the Guildford
Formation.
Figure 6:
Dunes underlain by silica sand of the Bassendean Sand at surface, view looking east
Future Work
The Company intends to drill additional infill holes at each of the Resource areas to increase
confidence, increase the Resources and supply additional samples for future bulk testwork.
The drill program is expected to commence in the March quarter 2019.
The Company will continue to pursue marketing opportunities and follow up on enquiries to
date.
Corporate
Appointment of International Sales Manager
On 27 November 2018 VRX Silica announced the appointment of Mr Yoonil Kim to the
position of International Sales Manager.
Mr Kim was born in South Korea where he completed his education, including degrees in
environmental management systems and international trade. He has had fifteen years’
experience marketing Silica Sand to glass manufacturers and foundries in Korea, Japan,
Taiwan, Thailand, Philippines, Malaysia, Cambodia and China.
He has a demonstrated capacity to engage glass manufacturers, paint manufacturers and
foundry clients in South East Asia and will be based in Kuala Lumpur, Malaysia, from where
he can easily service the Asian markets.
Ventnor views the appointment of Mr Kim as an important step in the Company’s plans to
become an exporter of high-quality Silica Sand to the Asia/Pacific region.
Change of Company Name
Shareholders at the Company’s AGM on 30 November 2018 voted unanimously to change the
Company name to VRX Silica Ltd and on 6 December 2018 Ventnor Resources Ltd advised the
market that as of that date VRX Silica Ltd will be the name of the Company; however the ASX
ticker code will remain as VRX.
The new Company name of VRX Silica Ltd removes any ambiguity as to the commodity in
which the Company is specialising and better reflects the Company’s objective of becoming
a large scale supplier of silica sand to the global market, and will be easily identified by
international customers and potential clients.
Option over Biranup Project and Farm-In JV
VRX Silica announced on 15 November that the Company had entered into an option
agreement with Metalicity Limited (ASX:MCT) (MCT) for MCT to acquire a 40% interest in the
Company’s Biranup Project (Project) and a farm-in and joint venture arrangement for the
balance of the Project. Biranup Project details are in the Company’s 2018 Annual Report.
The key terms of the option agreement are as follows:
-
MCT to pay the Company a $20,000 option fee to secure an exclusive 3-month option
period.
-
If the option is exercised, the purchase price for a 40% interest in the Project is $500,000,
payable in cash and/or MCT shares at MCT’s discretion.
-
Following exercise the parties will enter into a farm-in arrangement, whereby MCT may
earn a further 20% by spending $1 million and a further 20% by spending an additional $1
million (to an aggregate 80% interest), following which the parties will form a joint venture
to fund the Project on a pro-rata basis or the Company’s interest to dilute to a net smelter
royalty.
Three LOIs for Silica Sand Offtake
On 11 December 2018 VRX Silica Ltd announced that it has received three non-binding
Letters of Intent (LOIs) for the offtake of an aggregate 590,000 tonnes of silica sand per
annum from the Company.
The LOIs have been received from a diverse range of silica sand distributors in the AsiaPacific region – the Company’s primary target market for the supply of silica sand – to supply
silica sand to different countries for a range of industries.
VRX Silica noted at the time that the receipt of these three LOIs supported the Company’s
research that there is significant demand for silica sand products of the type capable of
production from the Company’s Arrowsmith and Muchea silica sand projects. This is a solid
foundation for the Company’s initial aim of establishing demand for more than 1 million
tonnes per annum from each individual project area.
Details of the distributors and the LOIs generally are set out below:
Si Resources Corporation – Philippines: Si Resources Corporation (SRC) is a wholly
owned subsidiary of Rock Energy International Corporation; during the last two decades it
has been one of the leading distributors of imported silica sand within the Philippines.
SRC is located in Manila South Harbour, Philippines, and supplies the Philippine glass bottle
manufacturing industry with 110,000 tonnes of silica sand annually as well as supplying
other industrial users of silica sand, creating a total annual demand of 290,000 tonnes.
SRC’s LOI covers the supply of this tonnage annually from the Company with pricing
dependent on final specification. The specification* sought by SRC can be met from the
Arrowsmith Silica Sand Project production.
Shanghai GEEYEAH International Trading Co., Ltd – China: Shanghai GEEYEAH
International Trading Co., Ltd (SGI) is located in Pudong New District, Shanghai, China and
is a leading supplier of silica sand for more than 15 years to the fibreglass market and more
recently to the solar panel cover glass market.
SGI’s LOI covers the supply of 200,000 tonnes per annum, subject to final price and
specification, for a period of five years. The specification* sought by SGI can be met from
the Muchea Silica Sands Project production.
Dong A Heung-Eop Mining Co., Ltd – Republic of Korea: Dong A Heung-Eop Mining
Co., Ltd (DAHEM) of Busan, Republic of Korea, has been one of the leading suppliers of
casting sand to the Korean foundry industry for more than 50 years.
DAHEM’s LOI covers the supply of 100,000 tonnes of high purity silica sand per annum with
pricing dependent on final specification. The specification* sought can be met from the
Arrowsmith Silica Sand Project production.
Capacity for Supply
The Company is confident from exploration and testwork conducted to-date that it can
readily meet the specifications* and tonnage sought under the LOIs from the Company’s two
silica sand projects in Western Australia - Muchea and Arrowsmith.
Events Subsequent
On 17 January 2019 VRX Silica Limited announced the lodgement of its second silica sand
Mining Lease Application, MLA70/1390 at its Muchea Silica Sand Project which is located
50km north of Perth.
The mining lease application includes 92% of the total previously announced Resource of 191
Mt @ 99.6% SiO2 (Muchea Maiden Resource of 20 November 2018) but is expected to
increase with deeper drilling than the hand-auger sampling previously undertaken to estimate
the Resource.
The Muchea Mining Lease Application MLA70/1390 has an area of 2,918Ha, see Table 8
below, and covers part of the Exploration Licence E70/4886, Figure 1, which was granted on
27/03/2017.
Table 8: Muchea tenement application details
Tenement
Holders
Application date
Area (km2)
MLA70/1390
Wisecat Pty Ltd
14/01/2019
29.2
CSA Global has reported the Mineral Resource which is located within the MLA boundary and
is summarised in Table 9, below.
Table 9: Muchea Silica Sand Mineral Resource estimate within MLA
Classification
Million Tonnes
SiO2%
Al2O3%
Fe2O3%
LOI%
TiO2%
Indicated
12.5
99.7
0.04
0.04
0.2
0.09
Inferred
162.7
99.6
0.04
0.02
0.2
0.08
Indicated + Inferred
175.2
99.6
0.04
0.02
0.2
0.08
* Note: Mineral Resources are reported only from within the VRX nominated MLA and form a subset of the
total Muchea Project Mineral Resources as reported to the ASX on 20 November 2018. Differences may
occur due to rounding.
Competent Persons Statements
The information in this Report that relates to Muchea Exploration Results is based on data
collected under the supervision of Mr David Reid, in his capacity as Exploration Manager. Mr
Reid, BSc (Geology), is a registered member of the Australian Institute of Geoscientists and
has sufficient experience that is relevant to the style of mineralisation and type of deposit
under consideration and the activity being undertaken to qualify as a Competent Person
under the 2012 edition of the “Australasian Code for Reporting of Exploration Results,
Mineral Resources and Ore Reserves”. Mr Reid consents to the inclusion of the data in the
form and context in which it appears.
The information in this report that relates to Mineral Resources is based on information
compiled by Mr Grant Louw who is a full-time employee of CSA Global, under the direction
and supervision of Dr Andrew Scogings, who is an Associate of CSA Global. Dr Scogings is
a Member of the Australasian Institute of Mining and Metallurgy and a Member of the
Australian Institute of Geoscientists. He is a Registered Professional Geologist in Industrial
Minerals. Dr Scogings has sufficient experience relevant to the style of mineralisation and
type of deposit under consideration and to the activity which he is undertaking to qualify as
Competent Person as defined in the 2012 Edition of the Australasian Code for the Reporting
of Exploration Results, Mineral Resources, and Ore Reserves (JORC Code). Dr Scogings
consents to the disclosure of information in this report in the form and context in which it
appears.
ASX Listing Rule 5.8.1 Summary
The following summary presents a fair and balanced representation of the information
contained within the Mineral Resource Estimate (MRE) technical report:
Silica sand mineralisation at the Muchea Project occurs within the Bassendean Sand,
which extends along the Swan coastal plains of the Perth Basin, parallel to the coast.
(ASX LR 5.8.1 geology & geological interpretation)
Samples were obtained from auger and aircore drilling. Quality of drilling/sampling and
analysis, as assessed by the Competent Person, is of an acceptable standard for use in
a Mineral Resource estimate publicly reported in accordance with the JORC Code. (ASX
LR 5.8.1 Sampling & 5.8.1 Drilling)
Major and trace elements apart from SiO2 were analysed using a four-acid digest
followed by Inductively Coupled Plasma Optical (Atomic) Emission Spectrometry (ICPOES) analysis at the Intertek Genalysis, Perth laboratory. Loss on Ignition at 1000°C
(LOI) was analysed by Thermal Gravimetric Analyser. SiO2 was back-calculated by
subtracting all ICP major and trace elements plus LOI from 100%, as this is the